Timing is everything (until it isn’t): navigating the timeline for bringing home building proceedings

The Background

The dispute arose from a multi-unit residential development in Meadowbank completed on 15 July 2014 by Wekan Pty Ltd (Developer) and Raysons Constructions Pty Ltd (Builder).

The Owners Corporation (OC) commenced proceedings in NCAT on 26 November 2020, over four months after the expiry of the six-year limitation period under the Home Building Act 1989 (NSW) (HBA). The claim was a statutory warranty claim for damages and included general building defects and structural defects.

Prior to the hearing, the Developer went into administration and the proceedings against the Developer were stayed under the Corporations Act 2001 (Cth). The claim proceeded against the Builder only.

NCAT proceedings

The OC claimed that it was entitled to an extension of the warranty period and relied upon the limited six-month extension allowed when the defect only becomes “apparent” in the final six months of the warranty period per s 18E(1)(e)-(f) of the HBA, which says in summary:

If a breach of warranty becomes apparent within the last six months of the warranty period, proceedings may be commenced within a further six months after the end of the warranty period; and a breach of warranty becomes apparent when any person entitled to the benefit of the warranty first becomes aware (or ought reasonably to have become aware) of the breach.

The Builder ran a limitation defence that the proceedings were out of time.

The Tribunal found in the OC’s favour and determined:

  1. that the OC was aware of the defects as early as 2014 but was not aware the defects amounted to breaches of statutory warranties until later when the OC obtained expert evidence; and
  2. that the OC was entitled to the extension of the warranty period, and the Builder was ordered to rectify the defects.

Internal NCAT appeal proceedings

The Builder appealed the determination based on seven grounds, the first ground being whether the Tribunal had made an error of law by finding that the OC could rely on the six-month extension of the warranty period.

The Appeal Panel only addressed the first ground and found that the proceedings were commenced after the six-year time period for major defects expired and therefore, the Tribunal did not have jurisdiction to hear and determine the issues between the parties and therefore, the application must be dismissed.

The Builder was successful, and the Appeal Panel upheld the appeal.

Supreme Court appeal proceedings

The Supreme Court upheld the appeal and found that the OC could rely on the six-month extension of the statutory warranty period.

Key takeaways of this decision:

The Court’s decision has ultimately provided us with more guidance in relation to the following:

  1. on what “becomes aware or ought reasonably to become aware”

The Court held that there are two limbs to the test. On its face, it asks whether “any” person entitled to the benefit of the warranty has either:

a) become aware; or

b) ought reasonably to have become aware of the breach.

The Court drew a distinction that just because an owner is aware of a defect, this does not mean that they should be aware that the defect is a breach of the statutory warranties as they are very different things.

The OC argued it only became aware of the true seriousness of the defects in the final six months of the limitation period when they received the expert reports. The Court agreed and said that whether defects are a breach of the statutory warranties is a legal conclusion which will usually involve further expert investigation to confirm.

  1. an awareness of the defect by owners is not sufficient grounds to bar the whole claim as each defect must be assessed separately along with its link to a breach of the warranties;
  1. the owner bears the onus of proof to demonstrate that they did not know about the defects. The Court found that where there is an issue of whether an owner has commenced action within the further 6 months, the onus rests with the owners to establish the facts that entitle it to rely on the extended time;
  2. owners can rely on the 6-month extension, but they must prove that they only became aware of the “breach” in the last 6 months of the warranty period;
  3. the Appeal Panel made an error in the way they interpreted the original NCAT determination (that the OC knew about the defects years earlier) and suggested that the errors could have been clarified by the parties via the slip rule; and
  4. given that the Appeal Panel of NCAT did not address all of the appeal grounds, the matter was referred back to NCAT.

Where do builders and developers go from here?

This decision has created significant implications for key players within the building and construction industry. Therefore,  builders and developers should note that:

  1. knowing when the warranty period for your residential building projects expire is beneficial;
  2. running a limitation defence can be difficult to defend as well as costly and time consuming (this case took four years to reach the Supreme Court and is still ongoing);
  3. considering commercial resolutions early on before proceedings are commenced as the Tribunal will likely make a work order for rectification in any event so any genuine defects should be addressed. This may avoid the risk of defending contested proceedings in the District Court or Supreme Court where the Court can only award damages not rectification; and
  4. seek legal advice well in advance of warranty periods lapsing if you are on notice of defective work by owners.

 

If you or anyone you know needs any assistance in relation to this, please contact Bradbury Legal who are specialists in this area, on (02) 9030 7400 or at info@bradburylegal.com.au.

Locked Out by Time: NSW Supreme Court Clarifies Long Stop Limits in Home Warranty Claims

In a decision that will resonate across the construction, insurance and strata management sectors, the Supreme Court of New South Wales has delivered a clear message: when it comes to statutory home warranty insurance, timing is everything.

The recent case of The Owners – Strata Plan No. 81376 v Dyldam Developments Pty Ltd [2025] NSWSC 438 (Dyldam Developments), decided by Justice Stevenson on 8 May 2025, underscores the unforgiving nature of statutory limitation periods under the Home Building Act 1989 (NSW)(HBA). This ruling has reinforced the strict limits of what can be claimed, when and how – particularly in relation to latent defects and historical correspondence.

Understanding the Framework

Home warranty insurance plays a vital role in protecting homeowners and strata schemes from defective residential building work in New South Wales. Under the HBA, builders and developers are required to obtain statutory warranty insurance for residential projects valued over a certain threshold ($20,000). This insurance provides cover to property owners in cases where the builder is insolvent, dead or has disappeared, and there are defective and/or incomplete works.

Within this statutory framework, two key provisions of the HBA govern the timing and scope of insurance claims:

  • Section 92(5) provides that a contract of insurance is in force for residential building work (the “original work”) extends to any further work carried out by the same builder by way of rectification of the original work. Accordingly, a separate insurance contract is not required in relation to the rectification work.
  • Section 103BC, often referred to as the “long stop” provision, imposes a strict limit of 10 years from the date of completion of the building work. After this period, no claim can be brought under the policy – regardless of when a defect is discovered or how serious it may be.

These provisions aim to balance consumer protection with commercial certainty for insurers and builders. However, in practice, they can have  consequences for owners who discover structural issues or latent defects years after completion.

Background – The Facts

The dispute in Dyldam Developments arose from a multi-unit residential development completed in 2012. Following the collapse of the builder and developer – both of whom entered administration in 2022 – the only active defendant remaining was Lumley Insurance (part of Insurance Australia Limited), which had issued the residential building insurance policy in 2006.

After discovering building defects, the Plaintiff, (the Owners Corporation), claimed that correspondence with Lumley Insurance in both 2012 and again in 2022 constituted formal insurance claims. They argued that the insurer remained liable for the defective works, despite the significant passage of time.

Lumley Insurance denied liability, asserting that the correspondence in question did not constitute valid claims under the policy and that any entitlement had been extinguished by the operation of the 10-year statutory limitation period – specifically, section 103BC of the HBA.

This case gave the NSW Supreme Court an opportunity to clarify the scope and operation of statutory limitation provisions in relation to home building insurance – particularly whether informal communications satisfy the requirements of a formal insurance claim, and how long stop limitation is to be applied.

The Dispute: What Constitutes a “Claim”?

At the heart of the case was whether the correspondence – letters sent in 2012 and again in 2022 – constituted valid claims under the home warranty insurance policy issued by Lumley Insurance. The Owners Corporation argued that the insurer’s obligations were triggered by these letters, as they related to building defects from work carried out by Dyldam Developments.

The insurer maintained that the communications did not meet the policy’s requirements for a formal claim – and, in any case, that the time limit for bringing a claim had long since expired.

Legal Terrain: A Matter of Interpretation

The case required careful consideration of statutory interpretation and the construction of the insurance policy. Key provisions of the Home Building Act examined by the Court included:

  • Section 92(5), which addresses how insurance policies apply to rectification work performed by the same builder;
  • Section 103BC, the so-called “long stop” provision, which caps liability at 10 years from the completion of work, regardless of when defects become known.

Justice Stevenson also considered foundational High Court authorities such as McCann v Switzerland Insurance Australia Ltd (2000)[1] and Project Blue Sky Inc v Australian Broadcasting Authority (1998),[2] along with recent guidance from the NSW Court of Appeal in Drummond v Gordian Runoff Limited CAN 052 179 647 [2024].[3]

The Decision: A Firm “No”

The Court was asked to determine several key questions, including:

  • Did the 2012 letter constitute a valid claim under the insurance policy?
  • Were the 2022 letters submitted within time to qualify as valid claims?
  • Could any statutory interpretation operate to circumvent the 10-year long stop?

The Court’s answer to all three questions was a resounding “no.”

Justice Stevenson held that the correspondence did not meet the policy’s definition of a claim. Even if it had, the 10-year long stop limitation period under section 103BC had expired. Section 92(5) did not operate to extend or reset the limitation period – the insurer’s liability was extinguished.

Why It Matters

This decision is a clear reminder to owners’ corporations, strata managers and construction professionals: the statutory protections afforded by home warranty insurance are strictly time-bound.  The clock starts ticking at the date of completion, not when a defect is discovered or discussed.

Insurers will welcome the certainty provided by the Court’s interpretation. Builders and developers should also consider the implications for rectification work and insurance coverage. Most importantly, property owners and strata committees must take early and formal steps when pursuing defect claims – delays can be fatal.

A Turning Point for Policyholders?

This judgment may prompt calls for legislative reform, particularly from strata and consumer advocacy groups. Given that many building defects are latent and may not be discovered until well after completion, the strict application of the 10-year long stop can leave property owners without recourse.

Whether Parliament will revisit the timeframes under the HBA remains to be seen. For now, however, the position is clear: home warranty claims must be made strictly within the timeframes prescribed by statute and the policy. Anything less will likely be dismissed – regardless of merit.

If you’re involved in construction disputes, strata law or insurance litigation, this case is essential reading. Feel free to reach out or connect for further discussion on its implications.

 

Bradbury Legal is a specialist building and construction law firm. If you or anyone you know requires advice or assistance, reach out to us on (02) 9030 7400, or email us at info@bradburylegal.com.au to see how we can assist you.

[1] 203 CLR 579; [2000] HCA 65.

[2] 194 CLR 355; [1988] HCA 28.

[3] NSWCA 239.

Not all Calderbank offers are created equal – 7 Rules for Drafting Enforceable Calderbank Offers

In construction disputes – where legal costs escalate quickly and project delays can be costly – Calderbank offers are a powerful strategic tool for early resolution and litigation cost management. However, not all Calderbank offers are created equal. To be effective, particularly when seeking to recover costs, a Calderbank offer must be drafted with precision, clarity and intent. A poorly constructed offer may be given little or no weight in costs proceedings.

Before diving into the drafting rules, let’s revisit the fundamentals.

What is a Calderbank Offer?

A Calderbank offer is a written offer to settle a legal dispute, made “without prejudice save as to costs.” It originates from the English case Calderbank v Calderbank [1975][i] and allows parties to negotiate privately without prejudicing their legal position – except when arguing about legal costs after judgment.

In practical terms, if the offer is unreasonably rejected and the opposing party fails to achieve a better result at hearing, the offering party can seek indemnity costs from the date the offer was made.

With that in mind, here are 7 key rules to ensure your Calderbank offer carries legal weight and maximises its intended cost consequences.

Rule 1: Clearly mark the offer “Without Prejudice Save as to Costs”

This label ensures the offer remains privileged during the substantive proceedings but can be disclosed when the issue of costs is determined. To avoid ambiguity, include the phrase prominently – both in the heading and opening paragraph. If this wording is missing or incorrect, the offer may be inadmissible in cost proceedings, undermining its strategic value.

Rule 2: Use precise, clear and unambiguous language

When it comes to Calderbank offers, ambiguity is the enemy of enforceability. As stated in Grabavac v Hart,[ii] the offer must leave the offeree in no reasonable doubt as to the nature and extent of what is being offered. The offer must:

  • Specify the exact amount offered or set out alternative settlement terms – such as completion of specific works or the granting of releases.
  • Identify the claims being resolved – whether it’s a global settlement or limited to a specific issue, such as claims for delay damages or variations.
  • Set out any conditions attached to the offer – such as execution of a deed of release, the timeframe for payment, or confidentiality provisions.

This clarity is particularly important in construction disputes, where overlapping claims are common.

Rule 3: Ensure the offer is reasonable and genuine

To be effective, a Calderbank offer must be a genuine attempt to settle, not just a tactical move. Offers that are clearly unrealistic or derisory may be disregarded by a court or tribunal. By contrast, offers supported by expert reports, quantum assessments or commercial analysis are more likely to carry weight and influence cost outcomes.

Rule 4: Include an express statement on costs consequences

Strengthen your position by making the cost implications explicit. For example, include a clause such as the following:

“This offer is made pursuant to Calderbank v Calderbank [1975] 1 All ER 333. In the event that this offer is not accepted and you fail to obtain a more favourable outcome, we will seek indemnity costs.”

This puts the recipient on clear notice and reinforces the seriousness of the offer.

Rule 5: Set a clear and reasonable deadline and acceptance process

The offer should clearly specify:

  • A reasonable timeframe for acceptance – generally at least 14 days unless the circumstances justify otherwise. The appropriate duration will depend on factors such as the complexity of the project, the nature of the offer and industry standards. For instance, in Meldov Pty Ltd v Bank of Queensland (No.2) [2015],[iii] a 12-day acceptance period was found to be sufficient.
  • The method by which acceptance should be communicated — such as by email, signed acceptance or written confirmation. This ensures that both parties are clear on how and when acceptance is valid.

Clearly setting out these details helps avoid disputes regarding the timing or manner of acceptance, particularly important in time-sensitive construction projects.

Rule 6: Explain why the offer should be accepted

While not mandatory, explaining the rationale behind your offer can help demonstrate its reasonableness. Courts have recognised that where one party clearly sets out why the other will fail, and that offer is unreasonably rejected, it may support an application for indemnity costs. As Lindgren J stated in NMFM Properties Pty Ltd v Citibank Ltd (No 2) [2001],[iv] where His Honour observed:

“…No doubt where a party puts with sufficient particularity to the opposing party the reasons why the latter must fail, yet the latter does not recognise the inevitable, this will be a factor pointing to an award of indemnity costs.”[v]

Importantly, where an application for indemnity costs is made, the burden lies with the applicant to establish that the rejection of the Calderbank offer was unreasonable.[vi]

Rule 7: Retain evidence of service and communication

Always serve the offer in a traceable manner – via email with read receipt, courier or registered post. You should retain copies of:

  • The offer letter and any attachments.
  • Proof of service.
  • Any correspondence or acknowledgements.

These records are critical if there is later a dispute about whether the offer was made, received or properly considered.

Key Takeaway

A Calderbank offer is far more than a procedural step—it’s a tactical instrument for shaping both the outcome and the cost consequences of litigation. In construction disputes, where issues are complex and stakes are high, the value of a well-drafted Calderbank offer lies in its clarity, reasonableness and procedural integrity. Draft it with precision to not only encourage early settlement, but also to protect your client’s position when costs are ultimately determined

Follow Bradbury Legal for practical insights into construction law and commercial litigation. We are a specialist firm in building and construction law, committed to delivering practical, expert advice.

Call us on (02) 9030 7400 or email info@bradburylegal.com.au.

[i] 1 All ER 333.

[ii] [1997] 1 VR 154 per Winneke P at 155.

[iii] NSWSC 2015.

[iv] FCA 480; (2001) 109 FCR 77.

[v] Ibid., per Lindgren J at 87.

[vi] MGICA (1992) Pty Ltd v Kenny & Good Pty Ltd (No 2) (1996) 70 FCR 236 at 240 per Lindgren J; Sural Spa v Downer EDI Rail Pty Ltd [2007] NSWSC 1292 at 8 per Einstein J.

When titles do not matter, but responsibility does: Personal liability for de facto directors in construction

Overview

The recent Supreme Court of New South Wales decision in Brown v Etna Developments Pty Ltd [2025] NSWSC 358 delivers a compelling reminder that company directors – and even individuals acting as de facto directors – can be held personally liable for negligent acts during construction projects. This case underscores the importance of clearly understanding the roles and responsibilities of company agents, particularly when their conduct effectively places them in a position of control, decision-making, or assumed responsibility. For developers, builders, and those managing construction operations, it reinforces the real personal risk of informal or decentralised decision-making structures.

Background

The plaintiffs, Edmund Brown and Irena Saric, owned a residential property adjoining a construction site managed by Etna Developments Pty Ltd (Etna). Building works were carried out by Nutek Construction Pty Ltd (Nutek). During excavation, both companies failed to implement adequate safety and geotechnical measures to protect the plaintiffs’ land.

A significant collapse followed, rendering the plaintiffs’ property ‘virtually worthless’, cutting off vehicle access, and creating an ongoing risk of further subsidence. Expert evidence confirmed that the excavation was the proximate cause of the instability. Of particular significance, two individuals, despite never formally appointed as directors, had overseen and directed key elements of the excavation.

Findings

The Supreme Court found both Etna and Nutek liable in negligence and trespass. However, through the course of the proceedings, Etna entered into external administration and Nutek entered into Liquidation. The Court also made critical findings about the personal liability of the individuals who had operated as de facto directors of Nutek.

Justice Rees found that these individuals had:

  • exercised operational control over the site;
  • made key decisions about how the works were carried out;
  • failed to obtain adequate geotechnical advice; and
  • ignored foreseeable risks to neighbouring properties.

The Court held that by assuming effective control, they had stepped into the role of de facto directors1 – and, in doing so, owed a personal duty of care to the plaintiffs.2 Their failure to take reasonable precautions, despite knowledge of the risks, amounted to actionable negligence.3 Damages were awarded against Etna and the liability of Nutek was apportioned between the individual defendants based on their respective levels of responsibility.

Key Takeaways

  1. Titles Are Irrelevant – Agency and Responsibility are Everything

A de facto director is a person who is not formally appointed but who performs the functions of a director. Courts will examine conduct, not corporate records, to determine if someone is effectively in control. Those who direct operations, make strategic decisions, or hold themselves out as ‘in charge’ may face the same liabilities as appointed directors.

This case confirms that personal liability is not limited to officially registered directors. Individuals who act with authority and influence over corporate decisions—particularly where safety is at stake—can be held personally liable.5

  1. Construction Work Involves Heightened Duties

Directors and controllers of construction projects must proactively obtain expert advice and comply with all relevant safety and engineering standards. Courts will not accept cost-cutting or ignorance as a defence to property damage.6

  1. Review Internal Governance and Insurance

Firms involved in construction projects should review their governance structures and ensure appropriate professional indemnity insurance is in place. Those exercising effective control must be clearly informed of their obligations—and the potential personal exposure.7

If you or anyone you know is involved in construction or development and would like advice on managing director liability, contractor oversight, or professional indemnity risk, Bradbury Legal is a specialist building and construction law firm. Contact us on (02) 9030 7400, or at info@bradburylegal.com.au

 

Footnotes

  1. Grimaldi v Chameleon Mining NL (No 2) (2012) 200 FCR 296 at [113]–[115]; ASIC v King [2020] HCA 4 at [46]–[55]; Deputy Commissioner of Taxation v Austin (1998) 28 ACSR 565 at 574–575.
  2. Perre v Apand Pty Ltd (1999) 198 CLR 180 at [103]–[105]; Bryan v Maloney (1995) 182 CLR 609 at 627–628.
  3. Smith v Jenkins (1970) 119 CLR 397 at 403–405; Hamilton v Whitehead (1988) 166 CLR 121 at 128.
  4. ASIC v King [2020] HCA 4 at [54]–[55]; Grimaldi v Chameleon Mining NL (No 2) (2012) 200 FCR 296 at [113].
  5. ASIC v King [2020] HCA 4 at [54]–[55]; see also Grimaldi at [113].
  6. Woolcock Street Investments Pty Ltd v CDG Pty Ltd (2004) 216 CLR 515 at [23]–[25]; Parsons v Raby [2007] NSWSC 1059 at [55]–[59].
  7. Hamilton v Whitehead (1988) 166 CLR 121; Walker v Wimborne (1976) 137 CLR 1 at 6–7 (per Mason J).

 

Freeze Now, Enforce Later: Understanding Freezing Orders in NSW

A freezing order, also known as a Mareva injunction, is a powerful legal tool designed to prevent a party from disposing of or dealing with assets before a judgment can be enforced. In New South Wales, these orders are frequently sought in cases involving fraud, insolvency or complex commercial disputes. Their central aim is to preserve the enforceability of a future court judgment by preventing the dissipation of assets in the meantime.

What Is a Freezing Order?

A freezing order is an interlocutory injunction that restrains a party from dealing with specified assets, usually pending the outcome of litigation. The purpose is not to give a plaintiff a security interest in those assets, but rather to preserve the status quo so that any eventual judgment can be enforced.[1] These orders are typically granted under Rule 25.11 of the Uniform Civil Procedure Rules 2005 (NSW) and are often sought ex parte (without notifying the respondent) to avoid alerting the other party and triggering the very asset dissipation the order is designed to prevent.

Criteria for Granting a Freezing Order

Courts apply strict and well-defined criteria when determining whether to grant a freezing order. The applicant must satisfy all of the following:

  1. Good Arguable Case
    The applicant must demonstrate a “good arguable” case on the substantive claim. In Lambros v Urbanlux Homes Pty Ltd (in liq)[2021][2], the Court clarified that while the case need not have a greater than 50% chance of success, it must be plausible and capable of serious argument—higher than speculative but lower than proof on the balance of probabilities.
  2. Real Risk of Asset Dissipation
    There must be credible evidence that the respondent is likely to dispose of, hide, or deal with assets in a manner that could frustrate the enforcement of a future judgment.
  3. Danger That Judgment Will Be Unenforceable
    The court must be satisfied that, without the order, there is a real risk that a judgment in favour of the applicant would be wholly or partly unsatisfied due to the unavailability of the respondent’s assets.
  4. Balance of Convenience and Interests of Justice
    The court must be persuaded that the benefit of preserving the applicant’s potential remedy outweighs the inconvenience or prejudice to the respondent. Courts will also consider whether an undertaking as to damages has been offered by the applicant to compensate the respondent if the order proves unjustified.
  5. Jurisdictional Nexus
    There must be a connection between the respondent or the assets and the jurisdiction. The Supreme Court of NSW must have authority over the respondent or the relevant assets.

Scope and Enforcement

Freezing orders can apply to a wide range of assets, including bank accounts, real property, shares and personal valuables. They can also extend to assets located both within and outside Australia. Additionally, these orders can bind third parties, such as banks that hold assets on behalf of the respondent.

Key Considerations for Applicants

While freezing orders are powerful tools for preserving assets, they are discretionary and exceptional remedies that courts do not grant lightly.[3] Applicants seeking a freezing order should be mindful of the following:

  • Undertaking as to damages: Applicants must be prepared to compensate the respondent if the order is later found to have caused unjust harm, particularly if the freezing order is ultimately unjustified.
  • Access to funds: Orders generally allow respondents to access funds for reasonable living or business expenses, as specified in the order.[4]
  • Full and frank disclosure: In ex parte applications, applicants are under a strict duty to disclose all relevant facts, including those adverse to their case.[5] A failure on the part of the applicant to do so may result in the order being set aside.
  • Proportionality: The scope of the order must be proportionate to the value of the claim and tailored specifically to the risk of asset dissipation.

In Bennett (bht Jones) v State of NSW & Anor [2022][6], the Court reaffirmed its cautious approach to freezing orders, highlighting the need for a real danger of asset dissipation supported by clear and reliable evidence. The case underscores the importance of thorough preparation and detailed investigation of the respondent’s conduct when seeking such relief.

Freezing orders are also particularly effective in situations involving allegations of fraud, misappropriation of funds or asset stripping. They are also increasingly used in cross-border litigation, given their availability against third parties or foreign respondents in certain cases.

Final Thoughts

Freezing orders are a powerful litigation tool, but they must not be sought lightly. As an extraordinary and intrusive remedy, they demand careful attention to the evidence, full disclosure and precise drafting. Courts will closely scrutinise whether the legal criteria—especially in an ex parte setting—have been properly met.

Notwithstanding, when used wisely, freezing orders can mean the difference between a hollow victory and an enforceable judgment—underscoring the value of a strategy that enables litigants to freeze now, enforce later.

 

[1]  Jackson v Stirling Industries Ltd (1987) 162 CLR 612; Cardile v LED Builders Pty Ltd (1999) 198 CLR 380.

[2] NSWSC 1615 at [39].

[3] Frigo v Culhaci [1998] NSWCA 88, approved in Cardile v LED Builders Pty Ltd (1999) 198 CLR 380 at [51]; Severstal Export GmbH v Bhushan Steel Ltd (2013) 84 NSWLR 141 at [57].

[4] Goumas v McIntosh [2002] NSWSC 713 at [23].

[5] See Rees J in Madsen v Darmali [2024] NSWSC 76 at [12]–[15].

[6] NSWSC 1406.

The Price of Refusal – costs consequences of unreasonably rejecting Calderbank offers

A Calderbank offer is a special type of settlement offer made in an attempt to resolve anticipated or commenced litigation and derives the name from the case that first established the relevant principles, Calderbank v Calderbank [1975] All ER 333.  It is special in that a valid Calderbank offer may:

  • if you are the successful party in litigation, increase the percentage of legal costs you recover from the unsuccessful party; or
  • if you are the unsuccessful party in litigation, decrease the percentage of legal costs you pay the successful party.

A properly advised litigant will be factoring legal costs into their overall litigation strategy and will use Calderbank offers to strengthen their position by either recovering more costs or paying less costs.  This “costs protection” element differentiates Calderbank offers from standard offers to negotiate or settle litigation.  It also forces a party receiving an offer to give careful thought to the risk involved in not accepting the offer given the potential consequences for legal costs recoverable or payable.[i]

The principles are encouraged by the courts and tribunals because they facilitate the efficient and economic disposal of litigation in accordance with modern case management principles which are directed towards avoiding waste and delay in litigation generally.[ii]

Costs of the proceedings

The costs of the proceedings are typically dealt with after there has been judgment on the substantive issues of the case.  This is because the practical result or outcome of the judgment often determines which party is responsible to pay costs.  This is known as the guiding principle that “costs follow the event” with the event being the practical result or outcome e.g. the plaintiff succeeded in their claim for damages for breach of contract.[iii]

Costs are ordinarily awarded on an “ordinary” basis[iv] but, in special circumstances, may be awarded on an “indemnity” basis.[v]  In simple terms, the indemnity basis (85-95% of actual costs) is a higher percentage of recovery of actually incurred costs compared with ordinary costs (65-75% of actual costs).  In short, the difference will generally be 10-15% higher if recovering on an indemnity basis.

However, costs are always in the discretion of the court or tribunal having regard to various factors. One factor that is weighed in exercising that discretion is the existence of Calderbank offers that were not accepted.  In particular, establishing that you issued a valid Calderbank offer that was a better outcome than the outcome that was obtained by proceeding to judgment may both affect:

  1. the party responsible for paying costs; and
  2. the “basis” on which costs will be assessed.

Examples

The examples below are not automatic or guaranteed outcomes given costs are always at the discretion of the court or tribunal[vi] and there are many competing factors that are taken into account such as delinquent conduct by the party that made the offer in the litigation.  The examples are presented for simplicity and ignoring competing factors that might arise.

Successful Plaintiff that makes an offer

Take the following example:

  • proceedings were commenced on 1 January 2024;
  • a valid Calderbank offer was made on 1 July 2024 by the Plaintiff to settle for $600,000 and rejected (unreasonably) by the Defendant; and
  • judgment was entered on 1 December 2024 in favour of the Plaintiff for $900,000.

As a matter of commonsense, the Plaintiff’s Calderbank offer would have been a better outcome for the Defendant had it accepted the offer rather than proceeded to judgment.

The law recognises this logic and gives effect to it by increasing the percentage of legal costs recoverable by the successful Plaintiff by using the indemnity basis for part of the overall legal costs payable by the Defendant.  Specifically, in our example, the consequence of unreasonably rejecting a Calderbank offer that was better than the ultimate outcome is that the court or tribunal may exercise its discretion to order that:

  • the Defendant pays the Plaintiff’s costs on an ordinary basis between 1 January 2024 to 1 July 2024 i.e. before the offer; and
  • the Defendant pays the Plaintiff’s costs on an indemnity basis between 2 July 2024 and 1 December 2024 i.e. after the offer.

In short, the successful Plaintiff recovers an overall higher percentage of part of their legal costs.

Unsuccessful Defendant that makes an offer

As a variation on that example, let us assume the following facts instead:

  • proceedings were commenced on 1 January 2024;
  • a valid Calderbank offer was made on 1 July 2024 by the Defendant to settle for $600,000 and rejected (unreasonably) by the Plaintiff; and
  • judgment was entered on 1 December 2024 in favour of the Plaintiff for $400,000.

As a matter of commonsense, the Defendant’s Calderbank offer represented a more favourable result for the Plaintiff than the judgment.  In that scenario, the court or tribunal may exercise its discretion to order that:

  • the Defendant pays the Plaintiff’s costs on an ordinary basis between 1 January 2024 to 1 July 2024 i.e. before the offer; and
  • the Plaintiff pays the Defendant’s costs on an indemnity basis between 2 July 2024 and 1 December 2024 i.e. after the offer.

In short, the unsuccessful Defendant manages to recover that part of their legal costs incurred only because the Plaintiff did not settle on reasonable terms.

To Consider

For completeness, the underlying concept of a Calderbank offer has been formalised in Division 4 of Part 20 of the Uniform Civil Procedure Rules 2005 (NSW) as “Offers of Compromise”, however those types of offers are outside the scope of this article.

Noting the costs consequences associated with making and rejecting Calderbank offers, it is crucial that litigants use them in a way that promotes settlement of disputes to achieve their “just, quick and cheap” obligations and, otherwise, to protect their own position on costs.

 

 

[i] Dr Martens Australia Pty Ltd v Figgins Holdings Pty Ltd (No 2) [2000] FCA 602 at [24]. Bluth v Boyded Industries Pty Ltd (No 2) [2024] NSWCA 194 at [43].

[ii] See section 56 of the Civil Procedure Act 2005 (NSW) (CPA).

[iii] See rule 42.1 of the Uniform Civil Procedure Rules 2005 (NSW) (UCPR); see e.g. New Island Developments Pty Ltd v New Island Investments One Pty Ltd (No 2) [2024] NSWSC 454 at [29].

[iv] In the courts, section 98(1) of the CPA and rule 42.2 of the UCPR. In the Tribunal, section 60(4) of the Civil and Administrative Tribunal Act 2014 (NSW).

[v] See rule 42.5(b) of the UCPR.

[vi] Section 98(1) of the CPA; see e.g. Whitney v Dream Developments Pty Ltd [2013] NSWCA 188 at [25].

Hedging your debt (certificates) – how much do you really owe?

When entering into a contract for the performance of building works, the roles and responsibilities of each party are generally defined well enough to ensure the contract can be performed in a mutually beneficial manner. Although, what happens when these responsibilities are affected by the interaction between two pieces of legislation?

In Warrane Design Construct Fit-Out Pty Ltd v Woonona Bulli RSL Memorial Club [2025] NSWSC 123, the Supreme Court of New South Wales considers this question, where payment obligations between a Builder, Principal and Subcontractor changed due to the simultaneous application of the Building and Construction Industry Security of Payment Act 1989 (NSW) (SOPA) and the Contractors Debts Act 1997 (NSW) (CDA).

Key facts

During December 2023, Woonona Bulli RSL Memorial Club Limited (the RSL Club) contracted with Warrane Design Construct Fit-Out Pty Ltd (the Builder) to undertake works to the RSL Club’s carpark and converting the bowling green to another parking space (the Works). Shortly after, to complete the Works, the Builder entered into a subcontract with All Civil Solutions Group Pty Ltd (the Subcontractor). In the following year, the Subcontractor subsequently obtained three debt certificates from the District Court of NSW each valued at $989,183.55, $1,102,958.87 and $464,008.78 for unpaid works which were then served on the RSL Club pursuant to sections 6 and 7 of the CDA.[i] These provisions effectively allow a subcontractor who was not paid and still owed for works that were carried out, to obtain that payment from the principal that engaged the contractor.

At the time, the RSL Club fully paid the first but only partially paid the value of the second certificate. It is important to note that these were monies that would have been paid to the Builder, not the Subcontractor, as the act of issuing the debt certificates effectively assigned the RSL Club’s requirement to pay the Builder under to the contract to the Subcontractor. [ii]

Following this, the Builder obtained an adjudication determination against the RSL Club pursuant to section 22 of SOPA, and successfully sought to enforce it by way of an adjudication certificate and garnishee order for just over $2 million.[iii] Throughout this process, the fact that the RSL Club had made payments to the Subcontractor was not raised as a contentious issue before the adjudicator.

In response to this, the RSL Club filed two separate sets of proceedings to quash the determination by $1,030,281.79, [iv] on the basis that they had already partly paid or at the very least remained liable to pay the Subcontractor under the CDA.[v] The RSL Club also sought to set aside the garnishee order until the conclusion of the first set of proceedings.

What did the Court say?

Justice Stevenson concluded that because the Subcontractors served the debt certificates onto the RSL Club and payments were made pursuant to the CDA, the $2,141,780.83 awarded overstated the amount the RSL Club owed the Builder by approximately $1.2 million. [vi]

His Honour concluded that it was proper for the garnishee order to be set aside as this would undermine the legislative purpose of sections 6 and 7 of the CDA.[vii] Justice Stevenson also affirmed that the interpretation and construction of both SOPA and the CDA should be done in a way that ensures their ‘harmonious interaction’.

What does this mean for you?

Occasionally, certain Acts interact with each other which create new implications for how contractors and principals are required to manage and undertake payments. Given the large role legislation plays in encouraging or requiring parties to fulfil their payment obligations, ensure you can keep track of these obligations or otherwise seek assistance.

[i] Contractors Debts Act 1997 (NSW) ss 6-7.

[ii]  Ibid s 8(1)-(2).

[iii] Building and Construction Industry Security of Payment Act 1989 (NSW) ss 22, 25.

[iv] Warrane Design Construct Fit-Out Pty Ltd v Woonona Bulli RSL Memorial Club Ltd [2025] NSWSC 123 [15] (Stevenson J) (‘Warrane’).

[v] Ibid [15]-[17].

[vi] Ibid [17].

[vii] Contractors Debts Act 1997 (NSW) ss 6-7.

Time’s up!

In Australia, our Limitation Acts impose strict time limits for commencing legal proceedings.

Time limits vary depending on the type of matter and the jurisdiction.

Limitation periods (often referred to as ‘statutes of limitations’) are a statutory barrier to prevent individuals or businesses from pursing claims after a period of time has passed since the ‘cause of action’ arose. The primary purpose being to balance the rights of parties and the effective administration of justice and, in practical terms, to ensure finality to potential claims.

Civil Claims

Generally speaking, civil claims have a limitation period of 6 years from the date of the cause of action.

What is the relevant limitation period applicable to building claims in NSW?

To work out the applicable limitation period, start with the legislation that gives rise to the action (e.g. defective building work in NSW would be the Home Building Act 1989 (NSW) and/or the Design and Building Practitioners Act 2020 (NSW) (DBPA)). If there is no relevant legislation, look in the limitation act for your relevant state or territory:

  • New South Wales – Limitation Act 1969(NSW) (LA)
  • Australian Capital Territory – Limitation Act 1985 (ACT)
  • Queensland – Limitation of Actions Act 1974(QLD)
  • Victoria – Limitation of Actions Act 1958(VIC)
  • Tasmania – Limitation Act 1974 (TAS)
  • Northern Territory – Limitation Act 1981 (NT)
  • South Australia – Limitation of Actions Act 1936 (SA)
  • Western Australia – Limitation Act 2005 (WA)

These Acts may not apply if the limitation period for a specific cause of action is prescribed by another Act.

At times, more than two pieces of legislation must be considered to determine a limitation period. In building defect claims, the statutory duty of care is not merely the statutory warranty periods under section 18E(1)(b) of the Home Building Act 1989 (NSW) of 6 years for major defects and 2 years in any other case. Under section 37 of the DBPA a person who undertakes construction work has a duty to exercise reasonable care to avoid economic loss caused by defective construction work.  Section 41 provides that the applicable limitation is 6 years under the LA and subject to the 10 year longstop under section 6.20 of the Environment Planning and Assessment Act 1979 (NSW).

The table below sets out some of the more common causes of actions (COA) and corresponding limitation periods in NSW.

 

Implications for individuals and businesses

Being informed of the limitation period for a cause of action is essential as it can have significant implications on the rights and obligations of individuals and businesses.  If a limitation period expires, it may be difficult or impossible to commence legal proceedings, even if a case has merit.

Understanding the limitation periods for potential causes of action allows claimants to bring a claim within time.

Bradbury Legal is a specialist building and construction law firm. If you or anyone you know requires advice or assistance regarding a potential claim and the application of limitation periods, reach out to us on (02) 9030 7400, or email us at info@bradburylegal.com.au to see how we can assist you.

 

[1] Section 14(1)(a) of the LA 

[2] Section 14A of the LA 

[3] Section 6.20(1) of the EPAA

[4] Competition and Consumer Act 2010 (Cth), Schedule 2 Section 18; section 14(1) of the LA 

[5] Section 14(1)(b) of the LA 

[6] Section 14(1)(b) of the LA 

[7] Section 16 of the LA 

Don’t let escalating losses from defects snowball into an avalanche of avoidable (and unrecoverable) losses

What is mitigation?

In the context of construction disputes, “mitigation” refers to the obligation of a person suffering loss to not act unreasonably in allowing loss they suffer to worsen and result in additional loss.[1]  It is not about whether there was some better or ideal way in hindsight[2], but whether what was done was reasonable.  The obligation is not overly burdensome and does not require the person suffering loss to go out of their way and against self-interest to avoid loss, merely to have acted reasonably in seeking to prevent themselves suffering avoidable losses.[3]

For example, if the owner of a building is having significant water ingress issues due to defective roof waterproofing installed by their builder, the loss directly caused by the builder is a recoverable loss for the owner.  But if that owner sat on their hands and allowed the water ingress to worsen or cause consequential damage resulting in a greater loss e.g. internal damage of floors, walls, and furniture etc., the failure to avoid that additional loss is a failure to mitigate.

The mitigation obligation will be shaped heavily by any contractual agreement between the parties and override general law principles.[4]

Avoidable losses are not recoverable

In that example, an owner failing to avoid losses that can be avoided by taking reasonable action is exposed to the risk that a court or tribunal may decide the owner themselves caused that additional, avoidable loss and will not be able to recover it.  This is the case even where the original cause of the loss is the builder or one of its subcontractors.

The reason for this is that the compensation principle only requires that the owner is restored (by rectification works or money in our example) to the position they would have been had the builder not performed defective works.[5]  Avoidable loss caused by an owner’s inaction is not caused by the builder, only consequent upon it.

Further, the person who claims the other has failed to mitigate loss is required to prove that failure.[6]  In our example, the builder bears the obligation of persuading the court or tribunal that some parts of the ongoing loss suffered due to the water ingress followed from the owner’s failure to take reasonable steps to halt the water ingress.

Costs of reasonable steps to avoid loss are recoverable

Fortunately, the costs of actions taken by an owner to prevent the suffering of avoidable loss are compensable.  However, such losses must not be too remote which refers to excluding recovery of losses that would not typically arise or would not have been foreseen by the parties at the time of entering their agreement due to the breach.[7]

Recovery is possible even where the costs of the reasonable steps exceed the likely cost of the avoided loss (with the builder having to prove steps were unreasonable).[8]  For clarity, it is not necessary for the reasonable actions taken to have actually succeeded in avoiding the loss for the costs to be recoverable.

Mitigating by allowing the original builder access to rectify

With those general points in mind, this article considers a specific type of mitigation scenario which is an owner’s obligation to allow the original builder to return to rectify defective or non-compliant work before engaging a third party to take over and then claim monetary compensation.  This obligation can exist in the contract between the parties, in statute[9], and otherwise at common law[10].

Determining whether or not an owner has acted reasonably is assessed against the factual circumstances of the dispute.  Helpfully, Justice Rees in Ceerose[11] distilled four key facts that will be relevant in determining the question:

  1. the extent and seriousness of the defects;
  2. the quality of any repairs effected by the builder;
  3. the builder’s engagement with the owner in respect of the suggested defects and proposed method of rectification, in short, has the builder responded in a timely manner, taken the complaints seriously and acted fairly; and
  4. the efficacy or perceived futility of continuing to negotiate with the builder.

In this mitigation scenario, given the obligation to prove the failure falls on the builder and the standard of what is reasonable conduct for the owner is not high, it will typically be difficult to establish a failure to mitigate with the owner being precluded from recovering the avoidable loss.  Justice Rees in Ceerose remarked on this when considering recent decisions on this specific mitigation scenario.[12]

Economic advantages to both owner and builder of rectification

The advantages to an owner of mitigating their loss by allowing the original builder to return include:

  1. Ordinarily, the original builder will undertake this work at no cost to the owner given contractual and statutory obligations[13] to do so.
  2. If certain defects or non-compliant works are worsening over time, urgent and proactive action by an owner to allow a builder access will generally be a reasonable step to mitigate avoidable loss. As mentioned above, losses that could have been reasonably avoided will not be recoverable by an owner given the true cause of those losses is the failure to avoid them.

Builders often prefer returning for the simple fact it is generally cheaper than paying the equivalent amount in money to an owner.  This is because a knowledgeable builder will have contractual rights to compel subcontractors to rectify issues in their work at no cost, or, if there is a cost, that cost is less in the original builder’s hands compared with a fresh third party builder (which will include contingencies for the cost of unknowns involved in remedial work).[14]

Provided the rectification work is performed in good faith and correctly, the parties’ interests are aligned in this scenario and resolution is achieved without protracted litigation and accompanying costs.

If you’re an owner in a situation where your losses may worsen and you need advice on what steps you can take, or you’re a builder dealing with an owner that is refusing access which is worsening any issues you may have originally caused, please contact our team on (02) 9030 7400 or at info@bradburylegal.com.au.

 

[1] The Owners – Strata Plan No 89074 v Ceerose Pty Ltd [2024] NSWSC 1494 (Ceerose) at [38]-[39] per Rees J and the references therein.

[2] Banco de Portugal v Waterlow and Sons Ltd [1932] AC 452 at [506].

[3] Karacominakis v Big Country Developments Pty Ltd [2000] NSWCA 313 at [187] per Giles JA.

[4] Ceerose at [37] per Rees J.

[5] Robinson v Harman (1848) 1 Ex 850.

[6] Ceerose at [40] per Rees J and the references therein.  See also section 18BA(3) of the Home Building Act 1989 (NSW).

[7] Wingecarribee Shire Council v Lehman Brothers Australia Ltd (in liq) (2012) [2012] FCA 1028 at [988] per Rares J.

[8] Arsalan v Rixon Nguyen v Cassim [2021] HCA 40 at [32] per Kiefel CJ, Gageler, Keane, Edelman and Steward JJ.

[9] For example, section 18BA(3) of the Home Building Act 1989 (NSW).

[10] See generally Ceerose at [53] per Rees J.

[11] Ceerose at [51] per Rees J.

[12] Ceerose at [48]-[50] per Rees J.

[13] For example, in a claim for breach of the statutory warranties contained in section 18B of the Home Building Act 1989 (NSW) or the statutory duty of care contained in section 37 of the Design and Building Practitioners Act 2020 (NSW).

[14] See also Ceerose at [41]-[43] per Rees J and the references therein.

By Slim Majority, the High Court in Pafburn Says No: Developers and Head Contractors Cannot Apportion Liability Under the DBPA!

In a narrow 4:3 ruling, the High Court of Australia in Pafburn Pty Limited v The Owners – Strata Plan No 84674 [2024] HCA 49 (Pafburn) has dismissed the appeal of a developer and head contractor, ruling that liability for breaches of the statutory duty under section 37 of the Design and Building Practitioners Act 2020 (NSW) (DBPA) cannot be apportioned under proportionate liability legislation. This highly anticipated decision significantly expands liability, holding developers and head contractors accountable for defects arising from the work of consultants or subcontractors.

The Facts

Background

The Owners Corporation of a North Sydney residential complex (the Owners) commenced proceedings against Pafburn Pty Ltd (the Builder) and Madarina (the Developer) for breaching their statutory duty of care under section 37 of the DBPA. The Owners claimed that the Builder and Developer failed to take reasonable care to prevent economic loss caused by construction defects. In response, the Builder and Developer sought to apportion liability for the defects among nine other concurrent wrongdoers involved in the construction, including the waterproofing contractor, the manufacturer and installer of the aluminium composite panels, the architect, the private certifier and even the local council. The Builder and Developer argued that, under Part 4 of the Civil Liability Act 2002 (NSW) (CLA), liability for the defects should be shared. The Owners contended, however, that the statutory duty under the DBPA was non-delegable, meaning the Builder and Developer could not shift responsibility for the defects to other parties that the Builder and Developer had delegated work to during construction.

Application to Strike Out Proportionate Liability Defences

The Owners sought to strike out the Builder and Developer’s proportionate liability defences. They argued that section 39 of the DBPA explicitly states that the statutory duty of care is non-delegable, preventing reliance on the proportionate liability provisions of the CLA. The Owners further contended that, under section 5Q of the CLA, the Builder and Developer should be treated as if they were vicariously liable for the negligence of those performing delegated work, including the alleged concurrent wrongdoers. As a result, the Builder and Developer should not be allowed to apportion liability for the defects to subcontractors or other parties involved in the construction work.

Key issue

The key issue was whether the Builder and Developer’s duty under the DBPA could be apportioned under the CLA, allowing them to share liability with other parties involved in the construction process.

 What did the Court say?

Primary Decision

The Supreme Court of NSW initially found that the Builder and Developer could plead the proportionate liability defences. Rees J rejected the Owners’ argument, determining that a claim for breach of duty under the DBPA was an apportionable claim under Part 4 of the CLA. Her Honour held that vicarious liability under section 5Q of the CLA applied to a defendant’s breach of a non-delegable duty in tort under common law, but not to the statutory duty under section 37 of the DBPA. This meant that the way in which parties led disputes remained largely unchanged.

Court of Appeal

The NSW Court of Appeal overturned the primary decision, ruling that the statutory duty of care under the DBPA is non-delegable. The Court found that section 39 of the DBPA expressly excludes the application of the proportionate liability provisions in Part 4 of the CLA. It also held that sections 5Q and 39(a) of the CLA treat breaches of the non-delegable duty as a form of vicarious liability, meaning the Builder and Developer’s liability cannot be reduced by the liability of others, thereby preventing any apportionment of liability for breaches of the statutory duty under the DBPA.

 High Court

 The Builder and Developer sought to appeal the Court of Appeal’s decision and reinstate Rees J’s orders. However, in a slim 4:3 ruling, the High Court dismissed the appeal, affirming that developers and head contractors cannot apportion liability for defects under the DBPA. The Court held that, under section 5Q of the CLA, they are vicariously liable for defects arising from the construction work, including those caused by subcontractors or consultants. Effectively, the Builder and Developer could not limit their liability by shifting responsibility to other parties involved in the construction process.

What does this mean for you?

Developers and head contractors who delegate construction work may not be able to apportion their liability under the DBPA. Depending on the circumstances, they may be vicariously liable (that is, 100% liable) for any economic loss caused by defects, including those resulting from the negligence of their consultants and subcontractors.

 Implications

 While owners of defective buildings will undoubtedly welcome the High Court’s decision. It will have several practical and potentially onerous implications for developers and builders:

  1. Increased exposure:
  • Developers and head contractors now face greater liability to exposure, leading to higher construction costs.
  1. Rise in cross-claims:
  • Developers and head contractors will need to pursue cross-claims against other parties involved in the construction to seek contribution for defects.
  • This complicates case management of proceedings, as defendants may struggle at the outset to identify other parties’ roles in the project, determine appropriate causes of action and balance the cost risks of joining third parties.
  1. Higher insurance premiums:
  • The removal of proportionate liability defences is expected to lead to higher insurance premiums and increased difficulty in obtaining insurance coverage for construction stakeholders.
  1. Limited scope (for now):
  • The decision currently applies only to developers and head contractors.
  • The High Court primarily focused on whether developers and head contractors can apportion liability, leaving the question unresolved of whether other parties, such as consultants or subcontractors (particularly when they have not delegated any part of construction works), can rely on apportionment defences.
  • Interestingly, the minority raised doubts about whether a certifier or local council, in performing their duties, even qualifies as “a person who carries out construction work” under the DBPA, raising further ambiguity about their potential liability under the Act.

Bradbury Legal is a specialist building and construction law firm. If you or anyone you know requires advice or assistance, reach out to us on (02) 9030 7400, or email us at info@bradburylegal.com.au to see how we can assist you.