Bradbury Legal
  • Home
  • Services
    • Contract Drafting & Negotiation
    • Corporate & Commercial Advice
    • Dispute Resolution
    • Project Management & Contract Administration
    • Property Development Advice
    • Security of Payment
  • Our People
  • Updates
  • Contact
  • Privacy Policy
  • Menu Menu
  • LinkedIn
  • Mail
  • Instagram
  • Facebook

‘The suspense is killing me’ – when do reference dates continue to accrue under the Security of Payment Act?

January 2017/in Security of Payment

The High Court has determined that a reference date is a precondition to a valid payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) with its landmark judgment in Southern Han Breakfast Point Pty Ltd (in Liquidation) v Lewence Construction Pty Ltd [2016] HCA 52.  Whether or not a reference date exists will continue to be contentious in security of payment disputes and the High Court decision is likely to lead to an increase in security of payment disputes coming before courts.

The decision also creates uncertainty around when a reference date will accrue and raises doubts about a number of Supreme Court decisions in respect of the accrual of reference dates and contracting out of the Act.  The High Court has adopted a much more literal interpretation of the wording of the Act than lower courts, which have regarded the objects and purposes of the Act as paramount.  In our opinion, the decision may ultimately result in an amendment to the wording of section 8 of the Act.

It is the first time the High Court has considered security of payment legislation in Australia and the decision will affect similar security of payment regimes to New South Wales, being all states and territories except Western Australia and the Northern Territory.

Facts

Southern Han Breakfast Point Pty Ltd (Southern Han) engaged Lewence Construction Pty Ltd (Lewence) to construct an apartment block for a contract sum of approximately $15.6 million (Contract).  On 27 October 2014, Southern Han gave Lewence notice to show cause in relation to alleged breaches of contract.  Despite alleged compliance with this request, the work was subsequently taken out of the hands of Lewence.  Lewence characterised the allegedly invalid taking of the work out of its hands as a repudiatory act and purported to accept that repudiation, with the effect that the Contract was terminated.

Under the Contract, reference dates accrued on the “8th day of each calendar month for work under the contract done to the 7th day of that month.”  A payment claim had previously been served on 8 October 2014 for work carried out to 7 October 2014, and on 4 December 2014 Lewence served what purported to be another payment claim.  This later claim failed to identify the reference date to which it related and concerned works carried out prior to 27 October 2014, including prior to 7 October 2014.

Decision and its effect

The High Court decision includes the following important points.

1. Reference date is precondition to a valid payment claim

The first issue before the court was whether a reference date is a precondition to a valid payment claim. This turned on the meaning and interpretation of section 13(1) of the Act, which defines those who are entitled to make a payment claim.  Lewence argued that the phrase “who is or who claims to be entitled to a progress payment” was purposefully expansive so as to apply to circumstances where a reference date had not arisen.  The court rejected this argument finding rather that the two-part description of those who may make a payment claim illustrates the distinction the Act makes between “present entitlement to progress payment and future ascertainment of the amount of the progress payment.”

From this the court held that all those making a payment claim must fall within the scope of section 8(1) of the Act, which grants such entitlement only “on and from each reference date under the construction contract” and as such concluded that a reference date under the contract is a precondition to the making of a valid payment claim.

2. Affirmation of one payment claim per reference date

The court provided further clarification as to the mechanics of section 13 generally, making it clear that not only must each payment claim be made in relation to a reference date, but that only one payment claim may be made in relation to a reference date.  A payment claim purportedly made that contravenes either of these requirements is not a payment claim under the Act, and is therefore incapable of ‘triggering’ the operation of Part 3 of the Act.  This affirms existing authority (see Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69 and Kitchen Xchange v Formacon Building Servics [2014] NSWSC 1602).

3. No reference dates accrue after termination (unless clear contractual intention)

A further issue before the court was the process by which a reference date is determined and ancillary to this, whether reference dates continue to arise after the termination of the Contract.  The court found that reference dates do not accrue after termination of the contract, unless there is a clearly expressed intention otherwise.

4. Accrual of reference dates can be suspended by operation of contract

The High Court found that there was no prohibition on Southern Han suspending payment and suspending the accrual of reference dates in reliance on clauses in the Contract.  The Court found that taking work out of Lewence’s hands had the effect of suspending the entirety of clause 37 of the Contract, including the accrual of reference dates.

5. When a reference date accrues depends on contract

The Court considered section 8(2) of the Act (set out below).

“(2)  In this section, reference date, in relation to a construction contract, means:

(a)  a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or

(b)  if the contract makes no express provision with respect to the matter—the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month.”

The Court confirmed that, if the Contract makes express provision for the accrual of reference dates, only section 8(2)(a) of the Act has work to do (i.e. the default reference date on the last day of each month only applies if a contract does not deal with reference dates).  Therefore, it is open to parties to agree on when reference dates will accrue and the circumstances around the accrual of reference dates.

It appears that the High Court was not required (or asked to) consider in what circumstances the no contracting out provision in section 34 of the Security of Payment Act may render such a clause void.

What does this mean for me?

The High Court decision is very important for construction industry stakeholders and the decision will affect principals and contractors in different ways.  All stakeholders should review and tailor construction contracts in light of the High Court’s decision.  Particular issues for principals and contractors to consider are set out below.

For principals

  • A reference date must exist for a contractor to make a valid payment claim.  A payment claim that is not in respect of a reference date will not be a valid payment claim under the Act.  Notwithstanding, principals should still always issue a payment schedule within 10 business days of receipt of a payment claim or a purported payment claim.  The payment schedule can still state that a reference date does not exist to validate the purported payment claim.
  • The High Court’s view is that the contract is king when it comes to determining when a reference date accrues.  Therefore, it is open to parties to agree on the circumstances when a reference date will arise.  Principals have previously attempted to impose conditions on the accrual of reference dates or provided that reference dates accrue after the occurrence of a specified event, but these conditions have generally been declared void for contracting out of the Act.  The High Court decision, which approves parties contracting to suspend the accrual of reference dates, provides some hope to principals that agreed conditions on the accrual of reference dates may be upheld.
  • To avoid doubt, construction contracts should state that reference dates do not accrue after termination of a contract.  Principals can take some comfort from the High Court’s decision in this regard.
  • Principals may wish to include other circumstances that result in suspension of payment and therefore also seek to suspend the accrual of reference dates.

For contractors

  • Contractors should ensure that there is a clear, unconditional and simple provision in their construction contracts for reference dates to accrue (on a monthly or milestone basis).
  • Contractors should also require an additional clause providing for reference dates to continue to accrue after termination of the contract, particularly if termination arises out of the principal’s breach of contract.  Alternatively, contractors should carefully consider their position before terminating a contract because reference dates will not accrue after termination and contractors will lose their rights to apply for adjudication.
  • Contractors should minimise the circumstances in which the accrual of reference dates and payment can be suspended to avoid being prevented from making a valid payment claim under the Act.
https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-01-31 06:56:382018-08-20 06:57:20‘The suspense is killing me’ – when do reference dates continue to accrue under the Security of Payment Act?

Summer of section 69: non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives

January 2017/in Security of Payment

The New South Wales Court of Appeal has confirmed that an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act) can only be quashed if there is a jurisdictional error of law.

The decision of the unanimous five-judge bench in Shade Systems Pty Ltd v Probuild Constructions (Aust) Pty Ltd (No 2) [2016] NSWCA 379 overturns the Supreme Court’s decision to quash an adjudication determination for non-jurisdictional errors of law on the face of the record.

The Court of Appeal decision also affirms its earlier decision in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421, which has been followed in numerous decisions of the Supreme Court of NSW (and in courts of other states and territories).

Court of Appeal’s decision

The question in this case was whether the Supreme Court can exercise its supervisory jurisdiction to quash an adjudicator’s determination for errors of law on the face of the record.  There was no dispute between the parties that:

  1. the adjudicator had made errors of law in his adjudication determination; and
  2. the errors of law were not jurisdictional errors.

Under section 69(3) of the Supreme Court Act 1970 (NSW) (SC Act), the Supreme Court has a supervisory jurisdiction empowering it to quash determinations of courts and tribunals that include errors of law on the face of the record.

Section 69(5) of the SC Act provides that section 69(3) of the SC Act (power to quash determinations for error of law on the face of the record) does not “affect the operation of any legislative provision to the extent to which the provision is…effective to prevent the Court from exercising its powers to quash or otherwise review a decision.”

In essence, the Supreme Court can quash a determination of a court or tribunal (including an adjudication determination) unless there is a legislative provision that prevents the Court from doing so.

Ultimately, the Court of Appeal found that the Supreme Court cannot exercise that jurisdiction to quash adjudication determinations if there are only errors of law on the face of the record and that there must be jurisdictional error for the Court to intervene.

The Court of Appeal’s decision considered the tension between section 69(3) of the SC Act and the Security of Payment Act.  In arriving at its decision, the Court of Appeal observed the following.

  1. The Security of Payment Act does not provide for an appeal mechanism, which supports the view that errors of law (other than jurisdictional errors of law) should not be subject of review by Courts.  On the other hand, there is no section of the Security of Payment Act that expressly precludes the Supreme Court from reviewing adjudication determinations for errors of law on the face of the record (as apparently contemplated by section 69(5) of the SC Act).  To resolve this tension, the Court of Appeal considered the content, structure and practical operation of the Security of Payment Act.
  2. The procedure provided for by the Security of Payment Act would be undermined if the Supreme Court could review adjudication determinations for errors of law on the face of the record.  The effect of such reviews would be to stifle the objects and purpose of the Security of Payment Act, which is to provide a quick mechanism for payment disputes and maintain cashflow in the construction industry.
  3. Section 25(4) of the Security of Payment Act provides that an adjudication determination cannot be challenged and allowing an appeal under section 69(3) of the SC Act would be inconsistent with the Security of Payment Act, but the Court concluded that this was a relatively weak factor.
  4. The consistent approach of courts in New South Wales (and other states) has been to follow the decision in Brodyn that adjudication determinations cannot be quashed only for errors of law on the face of the record.  The Court of Appeal concluded that no sufficient reason has been put forward to doubt the decision in Brodyn (as to there being any ground other than jurisdictional error to quash an adjudication determination).

The Court of Appeal found that there was a legislative intention by the scheme of the Security of Payment Act that adjudication determinations would not be subject of review for non-jurisdictional errors of law.

Obiter comments in Lewence put to bed

Interestingly, the five-judge bench of the Court of Appeal in Shade Systems was entirely different to the composition of the three-judge bench of the Court of Appeal in Lewence Constructions Pty Ltd v Southern Han Breakfast Point Pty Ltd [2015] NSWCA 288.  The Lewence decision was handed down in September 2015.

The Lewence decision, which was not referred to in Shade Systems, was overturned by the High Court on 21 December 2016, but not for reasons going to the difference between the issue of jurisdictional error and non-jurisdictional error.

In the Lewence Court of Appeal decision, obiter comments were made to the effect that adjudication determinations could be quashed for errors of law on the face of the record.  That decision was made by their Honours Emmett JA (the judge at first instance in Shade Systems), Ward JA and Sackville AJA.

In Lewence:

  • Emmett JA made no reference to quashing the determination for an error of law on the face of the record, however (as noted above) Emmett JA was the judge in first instance in Shade Systems who determined that adjudication determinations could be quashed for errors of law on the face of the record.
  • Ward JA said at [71]:

“This Court was not taken to adjudicator’s reasons to suggest that there was any error of law on the face of the record in relation to the existence of an available reference date.”

It is implicit in the above that her Honour considered such an argument was available to quash an adjudication determination.

  • Sackville AJA said at [126]:

The footnote at [1] referred to section 69 of the SC Act, which sets out the supervisory jurisdiction of the Supreme Court to quash court or tribunal proceedings that include an error of law on the face of the record.  Accordingly, his Honour clearly envisaged that adjudication determinations could be quashed for errors of law on the face of the record.

Having regard to the above, on a purely speculative basis, there may have been a different outcome in Shade Systems if the Court of Appeal bench had been comprised of different judges.

Summary

Unless there is a jurisdictional error of law, an adjudication determination will not be quashed by the Supreme Court.  That is so even despite errors of law by an adjudicator in their determination.  This decision, like Brodyn, is likely to be followed in states and territories with similar legislative regimes (all states and territories except the NT and WA).

There is clearly some divergence of opinion within the Court of Appeal on this issue and the Court of Appeal in Shade Systems has placed great significance on the objects and purposes of the Security of Payment Act evincing an intention for section 69(3) of the SC Act not to apply to adjudication determinations.  There is clear acknowledgement in the Shade Systems decision of the tension between section 69(3) of the SC Act and the purpose of the Security of Payment Act.

The unanimous five-judge verdict in Shade Systems is a clear signal that the Court of Appeal does not want to or see the need to tinker with the precedent established in Brodyn (and the volume of authority that has followed that decision).

It appears that High Court intervention will now be required before errors of law on the face of the record mean that an adjudication determination can be quashed by courts in New South Wales.  The High Court first intervened in security of payment legislation on 21 December 2016.  In that decision, the High Court adopted a literal and plain English interpretation (rather than purposive) interpretation of the Security of Payment Act.  A similar approach to reviewing the Court of Appeal’s decision in Sun Shades may result in adjudication determinations being reviewable for non-jurisdictional errors of law.  However, until the High Court intervenes, non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-01-24 06:57:272018-08-20 06:58:10Summer of section 69: non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives

Categories

  • Commercial Issues
  • Construction Regulation
  • Contract Issues
  • Disputes
  • Security of Payment
  • Uncategorized

Archive

  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • May 2023
  • April 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • May 2022
  • March 2022
  • February 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • February 2021
  • January 2021
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • November 2019
  • September 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • January 2019
  • November 2018
  • October 2018
  • September 2018
  • July 2018
  • June 2018
  • April 2018
  • March 2017
  • January 2017
  • December 2016
  • October 2016
  • June 2016
  • May 2016
  • April 2016
  • February 2016
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • April 2015
  • March 2015
  • February 2015
  • October 2014

Our Address

Suite 30.04, 201 Elizabeth Street
Sydney NSW 2000
02 9030 7400  |  [email protected]

About Bradbury Legal

We are a boutique law firm providing high quality, personalised legal services to the property, development and construction industries.

Liability limited by a scheme approved under Professional Standards Legislation © Copyright - Bradbury Legal
  • LinkedIn
  • Mail
  • Instagram
  • Facebook
Scroll to top