The battle of the ‘business days’: Understanding the ‘10-day timer’ under SOPA
When parties enter into a contract relating to the performance of construction work (or the supply of related goods and services), the party that provides these works or services is entitled to payment. The statutory basis for this principle is enshrined in Part 3 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA). As part of this, frameworks exist to ensure disputes over payment are resolved efficiently and quickly. These frameworks include outlining the definition of a ‘business day’[i] and the fact that progress payments under contracts are payable according to the terms stipulated within the contract (provided these terms are not contrary to SOPA).[ii]
Although, what happens when the day a payment claim is served becomes a contentious issue? In Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161, the NSW Court of Appeal considered this question. The court ultimately decided that a payment claim submitted after traditional ‘business hours’ was validly served. [iii]
Key facts
A contract was entered into between Roberts Co (NSW) Pty Ltd (Roberts) and Sharvain Facades Pty Ltd (Administrators Appointed) (Sharvain) to undertake construction works. Of note, clause 29.2(2) of the contract stated that if a ‘Notice’ was sent after 5:00pm on a ‘business day’ it was to be treated as received at 9:00am on the following business day. This was labelled by the Court as a ‘Deeming Clause’.[iv]
During the course of the contract, at 7:18pm on 28 February 2025, Sharvain emailed Roberts, enclosing a payment claim for the sum of $3,207,999.03 through Payapps.[v] Payapps quickly confirmed that the claim was submitted. Roberts subsequently issued the payment schedule on 17 March 2025.
A ‘business day’ is defined within SOPA to mean ‘any day other than a Saturday, Sunday or public holiday, or 27, 28, 29, 30 or 31 December’,[vi].
Therefore, if the 10-business day timer for the issue of a payment schedule started on 28 February 2025, after business hours, the payment schedule was due on 14 March 2025. However, if the timer began on 3 March 2025 (which was the next ‘business day’ Roberts could have received the payment claim), the payment schedule was issued within time on 17 March 2025. [vii]
What did the Court say?
The District Court of New South Wales had held that the Deeming Clause within the contract entered into by the parties operated in a manner that was inconsistent with section 4 of SOPA, and instead clause 29.2(2) attempted to amend the meaning of ‘business day’ by effectively postponing the point at which the 10-business day timer begins counting. Consequently, cause 29.2(2) was held to be void and the payment schedule was issued out of time.[viii]
On appeal, Roberts argued that the Deeming Clause could not be considered void ‘for all purposes’ as if it was to be considered as such, it would only be voided to the extent that it was drafted inconsistently with sections 4 and 14 of SOPA.[ix] Additional arguments were also put forward in relation to how clause 29.2(2) of the contract was exercisable under s 13A of the Electronic Transactions Act 2000 (NSW) which generally allows parties to facilitate contracts based on the exact time and date that electronic correspondence like emails or Payapps notifications are received by a party.[x]
Ultimately, the Court of Appeal upheld that relying upon the Deeming Clause was contrary to section 14(4) of SOPA, which provides a maximum 10-business day period to serve a payment schedule. This timeframe can be reduced to less than 10 business days, but any attempts to increase the amount of time provided to issue a payment schedule is contrary to SOPA. [xi]
What does this mean for you?
Contractors entering into agreements to undertake building or construction works should remain aware of key dates and obligations imposed on all parties both under the contract and SOPA. If you or anyone you know requires advice or assistance in relation to contract administration or rights under SOPA, contact us on (02) 9030 7400, or email us at info@bradburylegal.com.au.
[i] Building and Construction Industry Security of Payment Act 1999 (NSW), section 4 (‘SOPA’).
[ii] Ibid.
[iii] Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161 [52].
[iv] Ibid [21].
[v] Ibid [23].
[vi] SOPA, section 4.
[vii] Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161 [28]-[29].
[viii] Ibid [32].
[ix] Ibid [34]
[x] Electronic Transactions Act 2000 (NSW), section 13A.
[xi] Roberts Co (NSW) Pty Ltd v Sharvain Facades Pty Ltd (Administrators Appointed) [2025] NSWCA 161 [37].
