Bradbury Legal’s Back to Basics: Limitation Period
Part 1: Defects and Contracts – Which Limitation Period Applies?
Limitation periods are a foundational element of construction law claims, for all parties involved. In essence, a limitation period prescribes the time frame within which legal action must be initiated, such as a claim for defective work.
While the limitation periods applicable to various defects are clearly outlined in legislation (as detailed in the table below), complexities can arise in the context of construction contracts, particularly where multiple pieces of legislation may apply. This article examines several cases that help clarify these nuances.
To begin, it is useful to consider the basic limitation periods in New South Wales:
| Limitation Act 1969 (NSW) | For a breach of contract | 6 years from the breach |
| For a breach of deed | 12 years from the breach | |
| Home Building Act 1989 (NSW) (HBA) | For breach of statutory warranty resulting in a major defect | 6 years from the date of completion |
| For breach of statutory warranty resulting in a minor defect | 2 years from the date of completion | |
| Design and Building Practitioners Act 2020 (NSW) | For a breach of statutory duty of care | 6 years from the discovery of the defect |
A more complex issue arises in cases involving both a breach of statutory warranty and a breach of contract. The Supreme Court of NSW provided guidance on the appropriate limitation period to apply in such circumstances in Onslow v Cullen [2022] NSWSC 1257.
In January 2016, the builder (Onslow) entered into a contract with the owner (Cullen) to carry out residential building work under an HIA contract. Clause 39 of the contract expressly incorporated the statutory warranties prescribed by the HBA. In April 2017, Onslow ceased work prior to completion, and proceedings were subsequently commenced in August 2019 for a breach of contract, alleging both incomplete and defective works. Onslow contended that the defects in the completed works were minor defects, and therefore the two year limitation period was applicable. Conversely, Cullen maintained that the claim was in relation to breach of contract, meaning the 6 year limitation period should be applied.
The question posed to the Supreme Court was whether the breach of contract or the breach of statutory warranties applied, as the statutory warranties were incorporated into the contract. Justice Adamson drew attention to section 7(a) of the Limitation Act 1969 (NSW), which states:
Nothing in this Act (a) applies to an action or arbitration for which a limitation period is fixed by or under an enactment other than this Act or by an Imperial enactment (not being an enactment or an Imperial enactment repealed or omitted by this Act)…
This section clearly establishes that where legislation prescribes a different limitation period to that defined in the Limitation Act, this new limitation period will prevail. Accordingly, in the present case, it was determined that the claim would be for minor defects and so the two year limitation period displaced the six year limitation period for a breach of contract. Importantly, the incorporation of statutory warranties into the contract did not alter the fundamental nature of the owner’s claim.
The key takeaway from this decision is that, when dealing with limitation periods, one cannot rely solely on provisions of the Limitation Act in circumstances where new legislation has been enacted which dictates a differing limitation period.
For further analysis of limitation periods, the next Back to Basics article will examine the treatment of ‘tacked on’ defects and the relevant limitation rules that apply.
Bradbury Legal is a specialist building and construction law firm. Contact us on (02) 9030 7400, or at info@bradburylegal.com.au.
