Bradbury Legal
  • Home
  • Services
    • Contract Drafting & Negotiation
    • Corporate & Commercial Advice
    • Dispute Resolution
    • Project Management & Contract Administration
    • Property Development Advice
    • Security of Payment
  • Our People
  • Updates
  • Contact
  • Privacy Policy
  • Menu Menu
  • LinkedIn
  • Mail
  • Instagram
  • Facebook

Errors in Security of Payment: does one bad apple spoil the barrel?

July 2019/in Security of Payment

The Security of Payment regime is infamously inflexible and technical, demanding that parties and their lawyers adhere rigidly to the rules and procedure set out by the Security of Payment Act (SOP Act). The neglect of seemingly small details has led to entire adjudications being voided for lack of jurisdiction or for denial of procedural fairness.

In Rhomberg Rail Australia Pty Ltd v Concrete Evidence Pty Limited [2019] NSWSC 755, the Supreme Court of NSW was asked at what point will clerical errors lead to a judgment being quashed for want of natural justice and procedural fairness.

This case lends itself to the position that a respondent cannot challenge an adjudicator’s determination for denial of natural justice unless the circumstance in question is substantial enough to effect to the outcome of the determination.

In exercising their discretion as to whether natural justice has been denied, the Court will apply an assessment of reasonableness. In deciding on any relief, the Court may also determine that part of the determination that is affected by error can be severed from the part that is not.

Facts

Rhomberg Rail Australia (Rhomberg) engaged Concrete Evidence (Concrete) under a subcontract to lay reinforced concrete for the track slab in connection with a light rail project in Newcastle. The Contract Sum for the works was $3,146,278.36 (excluding GST). During the term, Concrete lodged and adjudication application for $1,061,800.61 (the balance owing under the subcontract and in respect of 119 variations), in which Concrete referred to a register of variations as being enclosed under Tab 7 of the application.

By way of clerical error, Tab 7 was incomplete, such that every other page was missing, resulting in reference to some variations being omitted. However, Tab 8 housed supporting documents in respect of all variations in the register under Tab 7, including for those variations omitted by clerical error under Tab 7. The submissions in Concrete’s application referred to some variations omitted in Tab 7. Both Rhomberg and the Adjudicator received copies of the application with the same clerical error.

Rhomberg served its adjudication response and stated in its submissions that “given the Claimant’s withdrawal of all variations which do not appear in Tab 7, the Respondent has not addressed those variations in this Adjudication Response.”

The Adjudicator, in providing his determination, said “the Respondent considers that the variations not shown in tab 7 have been withdrawn by the Claimant. I do not agree. The adjudication application is to be read as a whole including the amounts included in the payment claim, those disputed in the payment schedule and the submissions made.”

Rhomberg disputed the determination on the grounds that the Adjudicator denied it procedural fairness because the Adjudicator dealt with variations without giving Rhomberg an opportunity to make submissions in relation to them.

Judgment

Ball J found that there was no substantive denial of procedural fairness in respect of the omitted variations.

His Honour determined that in order to ascertain whether Rhomberg had been denied procedural fairness, the assessment would fall to whether Rhomberg ought reasonably to have concluded that Tab 7 was incomplete and that the adjudicator might deal with all the claims set out in Tab 8.

At [20], Ball J stated:

“In my opinion, a person acting reasonably would at least have appreciated that there was an inconsistency between Tab 7 and Tab 8 and therefore appreciated that there was at least a risk that the Adjudicator would proceed with his adjudication by reference to Tab 8 rather than Tab 7. That conclusion is reinforced by the fact that some of [Concrete’s] submissions specifically included references to variations that were not referred to in the Tab 7 schedule. It follows that [Rhomberg] ought reasonably to have appreciated that the Adjudicator might deal with all the Tab 8 variations. That is what the Adjudicator did. Consequently, [Rhomberg] was not denied procedural fairness.” (emphasis added)

Further, His Honour reasoned that the evidence to which Rhomberg argued it had no knowledge of, were the very variations that had been the subject of previous claims and correspondence between the parties, which “must be understood as referring back to what had previously been said in relation to those variations.”

To the question of whether Concrete was entitled to recover in respect of those variations omitted under Tab 7, Ball J at [25] said, reserving Rhomberg’s rights on appeal:

“[T]he adjudication determination should be set aside only to the extent that the Adjudicator determined that [Concrete] was entitled to recover in respect of variations on which [Rhomberg] was not invited to make submissions on and on which it could have made submissions consistently with s 20(2B) of the SOP Act.” (emphasis added)

His Honour found for Concrete, agreeing with their submissions, that Rhomberg was not denied procedural fairness because:

  1. it was evidenced that the Adjudicator might proceed to deal with the claims referred to in Tab 8;
  2. any denial of procedural fairness was not substantial as there were no further submissions of substance that Rhomberg could have made; and
  3. if there was a denial of procedural fairness, it did not affect the whole determination and Concrete should be entitled to recover the unaffected portion of its claim.

Commentary

The New South Wales Courts seem to be moving towards a more practicable position in their application of the SOP Act and in exercising their discretion on denial of natural justice considerations. Though other jurisdictions maintain a far stricter interpretation of the requirements of the SOP Act (see Niclin Constructions Pty Ltd v SHA Premier Constructions Pty Ltd & Anor [2019] QSC 91; Conveyor & General Engineering Pty Ltd v Basetec Services Pty Ltd and Anor [2014] QSC 30), the approach in New South Wales appears to prioritise the merits of a matter over strict statutory compliance.

There are two key takeaways from this decision:

  1. a denial of natural justice, of which a denial of procedural fairness is a species, may give rise to jurisdictional error on the part of an adjudicator to determine a payment claim under the SOP Act, in circumstances where a party could not reasonably have anticipated that either the adjudicator or the other party would rely upon the issue or principle concerned; and
  2. the generally accepted position in Fulton Hogan Construction Pty Ltd v Cockram Construction Ltd [2018] NSWSC 264, that the effect of a jurisdictional error will render a determination void, on the basis that a determination is a single determination of a single payment claim, is no longer the favored position in New South Wales. Following the position in the Court of Appeal in YTO Construction Pty Ltd v Innovative Civil Pty Ltd [2019] NSWCA 110, Ball J found that part of a determination affected by error can be severed from that part that is not so affected.

It would be an interesting exercise to consider what the Court’s position would have been had the clerical error only affected Rhomberg’s copy of the adjudication application and not the adjudicator’s (see section 17(5) SOP Act), and whether such a difference would amount to a denial of natural justice and lend itself to the same conclusions.

If you or someone you know wants more information or needs help or advice, please contact us on +61 (2) 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-07-22 00:53:242019-07-23 00:59:17Errors in Security of Payment: does one bad apple spoil the barrel?

A sunshine state for subcontractors: Queensland security of payment reforms

May 2019/in Security of Payment

The security of payment landscape has changed dramatically in Queensland in recent years. A number of measures are in now in effect which tilt the balance slightly towards claimants, and require respondents to be very vigilant so that their interests can be protected. Two other initiatives, the subcontractors’ charge regime and the project bank account regime, have also been modified.

These changes were all brought by the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (BIF Act), which received royal assent on 10 November 2017. Its provisions have recently come into effect.

The BIF Act repeals the previous regime, which is the Building and Construction Industry Payments Act 2004 (Qld) (repealed Act).

Security of Payment Changes

Even though the passing of the BIF Act is old news, the security of payment provisions only came into operation very recently, on 17 December 2018. They have retrospective effect, meaning the changes affect contracts even where they were entered into before this commencement date. The exception to this is where a payment claim was issued before this date and the matter remains “unfinished”. This will be for example where an adjudication is yet to be completed.

In general, the latest security of payment regime in Queensland is more claimant friendly. This is because the BIF Act allows claimants more time to make claims, and it requires faster and more comprehensive responses to claims by respondents.

This is consistent with the stated goals of the BIF Act. The Explanatory Memorandum stated that the goals of the changes were to improve the security of payment regime for subcontractors, to improve the accessibility of the security of payment legislation, and to increase the oversight of the Queensland Building and Construction Commission over the building industry.

Changes to “payment claim”

Under the BIF Act, payment claims no longer need to be “endorsed”, meaning they do not need to state that they are made under the Building Industry Fairness (Security of Payment) Act 2017.

An invoice can be a payment claim so long as it is a written document, it identifies construction work or related goods and services the subject of payment, it states the amount payable, and it requests payment (here, simply using the word “invoice” counts as a request).

Developers and contractors need to be very careful. An apparently unremarkable “invoice” might be a payment claim, which will trigger the security of payment regime. Further, there are serious consequences for respondents should they fail to respond to one of these (see below).

Many of the older rules about payment claims were copied over to the BIF Act now in force. Payment claims may still include amounts that were included in a previous payment claim. They must be given within a period of six months after the construction work was completed, unless the construction contract provides for a longer period of time (in which case, this longer period applies).

Reference dates after termination

The old reference date system is still in operation. Claims for progress payments may be made on a date or on dates provided for by the contract. If the contract does not state any date for claiming progress payment, such claims may be made on the last day of each month of work. Only one payment claim can be made on each reference date.

However, the BIF Act now addresses the murky situation of termination. This situation is not altogether clear in some states, but at least in Queensland we have clarity.

Now, where a construction contract is terminated, and the construction contract prevents reference dates from surviving past termination or is silent on the issue, the BIF Act states that a reference date will arise on the date that the contract is terminated.

It is assumed it does not matter which party terminates the contract, though the BIF Act does not say either way.

Payment schedule

The requirements for a valid payment schedule remain broadly unchanged. However, the time limits for a respondent to issue a payment schedule have been changed.

Under the repealed Act, different times for responding to payment claims were imposed depending on whether the claim was “standard” (equal or below $750,000 excl. GST) or “complex” (above $750,000 excl. GST).

Now, no matter if a claim is for $1,500 or $1.5 million, a respondent has 15 business days to respond to a payment claim. Where the contract stipulates less than 15 days to provide a payment schedule, this reduced time limit will apply.

This is more time to respond to standard payment claims, but for some complex payment claims it is less time to respond.

Consequences of no payment schedule

Failure for a respondent to provide a payment schedule prevents the respondent from giving an adjudication response. This is old news.

However, now in Queensland if the respondent does provide a payment schedule and the matter proceeds to adjudication, the adjudication response by the respondent cannot contain reasons that were not already included in the respondent’s payment schedule.

Previously the repealed Act allowed for the introduction of new reasons for withholding payment where the claim for payment was complex (over $750,000). The change to prevent the use of reasons not previously stated brings the Queensland regime in line with other East Coast regimes like NSW and Victoria.

However, unusually in Australian jurisdictions, failure by a respondent to provide a payment schedule is now also:

  • an offence, with a maximum penalty of $13,055 for individuals or up to $65,275 for corporations

and

  • a ground for disciplinary action under the Queensland Building and Construction Commission Act 1991 (Qld).

The only time a respondent does not need to issue a payment schedule is if the respondent pays the payment claim in full on or before the due date for the progress payment.

If the respondent disputes the claim or intends on paying it but after the due date, it is essential that it issues a payment schedule.

No second chance for payment schedule

The BIF Act has abolished the so-called “second chance” that a claimant was required to give to a respondent prior to commencing adjudication or court proceedings.

Previously, under the repealed Act, where a respondent failed to provide a payment schedule by the deadline in response to a payment claim, the claimant was required to notify the respondent that it may serve a payment schedule. The respondent then had five business days to take advantage of this second chance and produce the payment schedule. Only when it failed the second time was the claimant permitted to adjudicate or litigate the claim.

This is no longer the law.

Now, where no payment schedule is received by the claimant on time, the claimant can proceed immediately to adjudication.

If the claimant wishes to instead use court proceedings to recover the unpaid portion, it must give a warning notice of at least five business days to the respondent that the claimant intends to litigate. However, this is not a second chance – it does not allow the respondent to provide a payment schedule.

Extended time to make adjudication applications

The deadlines for claimants to make an adjudication application were extended by the BIF Act as follows:

  • Where the respondent fails to issue a payment schedule and fails to pay the full amount stated in the payment claim – 30 business days after the due date for payment, or 30 business days after the last day that a payment schedule could have been given by the respondent, whichever is later (previously: 10 business days);
  • Where the respondent states an amount owing in the payment schedule that is less than the amount stated in the payment claim – 30 business days after receipt of the payment schedule (previously: 10 business days);

In one situation, the deadline remains unchanged from before. This is where the respondent issues a payment schedule but fails to pay the whole or any part of an amount stated therein. This deadline for making an adjudication application remains 20 business days after the due date for payment. Some sources, including the explanatory memorandum of the BIF Act, state incorrectly that this deadline is 40 business days.

The upshot is that for respondents, the period of time after a payment claim is received during which the prospect of an adjudication looms, has been increased.

In addition to these time requirements, the adjudication application made by the claimant must:

  • be in approved form,
  • be made to the registrar,
  • identify the payment claim and payment schedule to which it relates,
  • include the prescribed fee, and
  • be served on the respondent.

One example of form is that for claims under $25,000 the submissions cannot exceed 10 pages in total.

Adjudicator

Adjudicators must now accept a referral to decide an adjudication application unless they have a reasonable excuse. They must do this within 4 business days of the referral being made.

Adjudicators now have the power to consider the conduct of both the claimant and respondent and allocate costs for the adjudication based on this. The adjudicator can consider a number of factors, including whether the adjudication was commenced or defended without reasonable prospects of success, and any reasons given by the respondent for not making the progress payment.

Parties must be careful about adjudicating claims without merit or unnecessarily delaying these processes, or they risk paying the other party’s costs.

Changes beyond Security of Payment

Apart from the amendment and consolidation of security of payment provisions, the BIF Act also introduced or amended a number of other regimes. Two are discussed below.

Project bank accounts for large contracts

The BIF Act introduces the Project Bank Accounts (PBAs) regime, for government building and construction projects valued between $1 million and $10 million (but not engineering infrastructure projects).

The regime will also expand and become mandatory for non-government projects valued at over $1 million, where over half of the contract price is for building work. The government has said this expansion will occur sometime in 2019 but more details are not yet available.

What are PBAs? They are bank accounts where progress payments and retention monies are held in trust; they cannot be touched by principals and head contractors in the way that regular moneys can. This is to protect subcontractors from head contractors, who traditionally receive the totality of the funds and sometimes fail to pass this down to subcontractors.

Penalties apply for head contractors undermining these reforms, such as where they fail to set up a PBA when required, or they end a PBA without authorisation. The maximum penalty in either case is 500 penalty units, which can amount to $326,375 for a corporation.

Subcontractors’ charges

The BIF Act also repealed the Subcontractors’ Charges Act 1974 (Qld), and took for itself many of the provisions of this Act. Most of the old subcontractors’ charge regime lives on, with a few small changes.

Ordinarily, a developer or principal owes money to builders (“contractors” in the BIF Act), who themselves owe money to subcontractors. Payment for work flows from the top through this hierarchy.

The subcontractors’ charge regime allows certain subcontractors to lodge charges over moneys that are otherwise owed by a principal to a contractor higher up in the hierarchy. The charge can be lodged by providing a notice to the contractor and the developer. The contractor then either accepts the liability, in which case the developer pays the subcontractor directly, or otherwise the contractor disputes the claim, and the amount is secured while court proceedings decide the matter.

Subcontractors should note that deadlines apply for issuing the notice, and once the money has passed from the developer to a contractor, it cannot be the subject of a charge.

This subcontractors’ charge regime remains broadly unchanged under the BIF Act. However, there are new provisions introducing certain offences:

  • It is an offence for a contractor to fail, within 10 business days of being requested, to provide certain information about the party who engaged the contractor and certain information about securities in existence for the contract.
  • Similarly, it is now an offence for a contractor to fail to give within 10 business days a written response to a notice by a subcontractor.

Both offences attract a maximum penalty of $2,611 for an individual and $13,055 for a corporation.

Conclusion

Overall, principals and contractors must be on their toes when receiving documents from other contracting parties.

The Queensland government has made significant changes to the security of payment procedure.

The BIF Act has combined three of the largest pieces of building regulation into one piece of legislation, putting the security of payment regime, the subcontractors’ charge regime, and the project bank account regime under one roof.

It has also introduced offences that penalise contractors and principals for their failure to comply with these regimes.

These changes affect every building contract in some way and are progressively coming into effect. It is essential that builders and developers are across them, as ignorance of these changes will not exempt them from some hefty financial penalties.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-05-14 23:25:052019-05-14 23:25:05A sunshine state for subcontractors: Queensland security of payment reforms

Security of payment: no work, no pay

May 2019/in Security of Payment

Participants in the commercial building industry generally rely on security of payment legislation to resolve payment disputes. As a preliminary means of recovering money under a construction contract, those in the industry are usually keen to hear of developments regarding a court’s interpretation of the legislative provisions.

Shape Australia Pty Ltd v The Nuance Group (Australia) Pty Ltd [2018] VSC 808 (‘Shape’ and ‘Nuance Group’) recently considered two issues under the Building and Construction Industry Security of Payment Act 2002 (Vic) (the ‘Act’), namely:

  • whether a reference date can be ‘refreshed’ for a payment claim when there has been no further work carried out since the previous reference date; and
  • whether an amount in a payment claim which attempts to recoup liquidated damages (previously offset in a payment schedule) constitutes an ‘excluded amount’ under the Act.

Background

In July 2016, Shape and Nuance Group entered a contract for the demolition and associated works at Melbourne International Airport.

On 2 March 2018, Shape issued payment claim #13 for $3,533,233.84. Nuance Group responded with a payment schedule stating the amount payable as nil. Shape applied for adjudication for a reduced sum of $2,243,105.55.

On 13 April 2018, a First Adjudication Determination for the sum of $1,400,007.12 issued, which after review instigated by Nuance Group, was reduced to $1,216,715.72.

Nuance Group challenged the validity of the original and reviewed determinations and, on 2 June 2018, in Nuance Group (Australia) Pty Limited v Shape Australia Pty Limited [2018] VSC 362 the Court quashed the determination on the basis that the adjudicator had “failed to perform his basic and essential function” under the Act.

Subsequently:

  • On 10 July 2018, Shape issued payment claim #14 for $1,285,579.62 which included “uncontested individual line items claimed in payment claim #13”. Nuance Group responded with a payment schedule stating the amount payable as nil.
  • Shape applied for adjudication, and on 23 August 2018, a Second Adjudication Determination issued which essentially declared the claim invalid for want of a valid reference date and that (in any event) the amount payable was nil on the basis that the claim was for an excluded amount.
  • Shape applied for orders remitting the first or second adjudication determination for review.

Decision

Was the payment claim invalid for want of a reference date?

Section 9(1) of the Act provides that there must be a valid reference date to avail rights for a person to a progress payment. A payment claim must be supported by a valid reference date, which is a precondition to an adjudicator making a determination under the Act.

Clause 42.1 of the construction contract entitled Shape to make payment claims on the 28th day of each month, and that such claims should include “the value of work carried out by the contractor in the performance of the contract to that time …”. On that basis, the Court considered that the requirement for work to be carried out “to that time” established a threshold for making a claim.

Payment claim 14, which had a reference date of 28 June 2018, was identical to payment claim 13, which carried a reference date of 28 February 2018. No further work had been carried out since issuing payment claim 13 and accordingly, 28 February was the last available reference date under the contract.

It followed that payment claim 14 was invalid for “want of a reference date”. The claim was either made in respect of the (same) 28 February reference date and therefore in breach of the Act, or a claim served out of time, namely, outside of the three-month period prescribed by the Act.

Shape’s application was dismissed, the Court agreeing with the adjudicator’s determination and finding nothing further to conclude otherwise.

Are liquidated damages an excluded amount?

The Act sets out certain classes of amounts that are “excluded” and must not be taken into account when calculating an amount of a progress payment. Essentially, excluded amounts include certain variations of the construction contract, amounts claimed for compensation due to the “happening of an event” (latent conditions, time-related costs and changes in regulations), amounts claimed for damages in relation, or incidental to, a breach under the construction contract or other claims arising at law.

The concept of an excluded amount in the Victorian Act underpins a key objective, namely, to facilitate cashflow within the industry by dealing with payment disputes promptly, whilst maintaining the parties’ legal rights to argue more complex issues later.

The Second Adjudication Determination declared the amount payable in the claim as nil on the basis that “…the entirety of the purported claim was for an excluded amount, being an attempt to recoup the first defendant’s asserted entitlement to liquidated damages”.

The Court confirmed this decision, reiterating the adjudicator’s findings that:

  • when the individual items listed in payment claim 14 were “adjusted and reconciled” the total equated “to the amount of Nuance Group’s asserted entitlement to liquidated damages”; and
  • the amount claimed could be “explained on no other basis, given no new work had been performed and the other claims in payment claim 14 [had] been satisfied”.

Takeaways

Seabay Properties Pty Ltd v Galvin Construction Pty Ltd [2011] VSC 183 determined that a set-off claimed in a payment schedule (by way of a deduction in response to a payment claim) constitutes liquidated damages and is therefore, an excluded amount for the purposes of the Act.

The present case however confirmed that an attempt to recoup liquidated damages through a payment claim will also constitute an excluded amount.

Industry participants should take note that:

  • Liquidated damages claimed as an offset in a payment schedule as well as amounts claimed in a payment claim to recoup liquidated damages are excluded amounts for the purposes of the Victorian security of payment legislation.
  • Claimants wishing to dispute liquidated damages should do so at the time they are levied. Where offsets have previously been raised in a payment schedule and the corresponding payment claim settled, a challenge to these levies in a subsequent payment claim will likely be considered an excluded amount.
  • If the right to make a payment claim under a construction contract is subject to the carrying out of work ‘up to the time’ for making the claim, there will be no available reference date unless work has been carried out since the last reference date.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-05-14 23:18:262019-05-14 23:18:26Security of payment: no work, no pay

Does a payment claim survive the termination of a contract for convenience?

May 2019/in Security of Payment

Security of payment legislation continues to receive significant attention across Australia’s building and construction landscape, with many cases being deconstructed to shed light on a court’s interpretation of various provisions.

Impero Pacific Group Pty Ltd v Bonheur Holdings Pty Ltd [2019] NSWSC 286 recently established that, despite a construction contract being terminated for convenience, a contractor may still claim for work carried out between the last accrued reference date and the termination date. Much will depend on the wording of the contract.

The decision diverges from previous case law which holds that a contract terminated for convenience does not provide ongoing reference dates, and consequently no entitlement for a contractor to claim for work carried out between the last reference date and termination.

Background

The contractor, Impero Pacific Group Pty Ltd (Impero) entered into a contract with Bonheur Holdings Pty Ltd (Bonheur), as principal, for construction of a residential strata complex, with a completion date of 1 March 2019.

The reference date, for the purposes of making payment claims was the 25th day of the month.

Crucially, the contract contained a termination for convenience clause (clause 39A), allowing the principal at its discretion to terminate the contract and complete any part of the works either itself or through another party. If invoked, the contractor would be entitled to payment for certain works carried out to the date of termination that would otherwise have been payable if the contract had not been terminated.

The contract was terminated for convenience by Bonheur on 29 or 30 October 2018.

Impero served a payment claim on 27 November 2018 for approximately $1.4 million relating to work undertaken between the last reference date being 25 October 2018 and the termination date, namely 29 or 30 October 2018.

Bonheur failed to respond to the claim as required under the Act and Impero sought judgement from the Supreme Court.

Bonheur argued that the payment claim was invalid as it was not supported by an available reference date pursuant to clause 8 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘Act’).  It contended that if the contract was terminated for convenience, “the Act cannot be used to obtain a progress payment for work done between the last contractual progress payment date and the date of termination.”

It was also submitted that, if Impero did have a right to a progress payment, it was “limited to part only” on the basis that it had claimed for items not within the scope of the Act and therefore no judgement could be obtained.

Impero argued that on construction of clause 39A, termination resulted in the creation of a new reference date and a consequential entitlement to claim and receive payment.

Decision

Justice Parker was not persuaded by the principal’s submissions and ordered the judgement sought by Impero.

The Act provides that on and from each reference date under a construction contract a person is entitled to a progress payment for work carried out under the contract.

Justice Parker acknowledged that under the current Act “there is no entitlement to a progress payment, and there can be no valid progress claim, unless there is an available reference date”. A reference date is defined as:

“(a)    a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out…under the contract, or

(b)     if the contract makes no express provision with respect to the matter – the last day of the named month in which the construction work was first carried out…and the last day of each subsequent named month.“

The last reference date prior to termination (on 29 or 30 October) was 25 October, which would have been available to claim for work carried out up to that date, but not beyond. Had the contract not been terminated, the next available reference date would have been 25 November.

Justice Parker considered the present matter in the context of previous cases and clause 39A of the construction contract. Clause 39A provided an entitlement for Impero to claim for work carried out under the contract up to the date of termination, and crucially this clause expressly stated that it would survive termination.

In the circumstances it was determined that “termination of the contract gave rise to a fresh reference date for the purposes of the Act“ and the entitlement for Impero to claim up to termination.

As to the contention that Impero’s right to a progress payment, if awarded, should be limited to part only, Justice Parker confirmed that “the Act does not permit the Court to make its own assessment of the extent to which the claimed amount represents payment for construction work or the supply of related goods or services. In that sense, it is an all-or-nothing provision.” The opportunity for a principal to argue that items fall beyond the scope of the Act arises by serving a payment schedule in response to a contractor’s payment claim. In the present case, the principal failed to do this.

Key takeaways

  • The exercise of a right to terminate a construction contract for convenience will not prevent a contractor from claiming for work carried out up to the termination date;
  • Progress claims should specify the works carried out between the last accrued reference date and the date of termination and relate only to works defined within the scope of the Act; and
  • Principals who terminate a contract for convenience should anticipate that a contractor may make a claim up to the date of termination. Items considered to be claims beyond the scope of the Act should be identified in the payment schedule.

Readers should be aware that Justice Parker makes it clear that termination for convenience is not the same as termination for breach nor is it similar to accepting the repudiation of the other party. The situation may be different in these cases. The High Court of Australia has previously ruled that in these cases, unless the contract expressly provides so, reference dates do not accrue after termination or accepted repudiation.

Where to next?

Determinations such as this are frequently analysed, particularly as participants in the building and construction industry await reforms yet to commence under the Building and Construction Industry Security of Payment Amendment Act 2018 (NSW). For more details on these amendments, click here.

Upon commencement of the current reforms proposed, the reference date system will be abolished, and a contractor will be able to make a progress claim for work carried out up to the date of a terminated contract, whether the contract is terminated for convenience or otherwise.

The policy behind these amendments is to discourage principals from strategically terminating a contract primarily to avoid a final payment claim being made under the Act.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-05-14 22:43:302019-05-14 23:45:28Does a payment claim survive the termination of a contract for convenience?

The Fantastic Fourth: another NSW Security of Payment amendment

March 2019/in Security of Payment

On 21 November 2018, the NSW Houses of Parliament passed the Building and Construction Industry Security of Payment Amendment Act 2018 (Amendment Act). This will amend some provisions of the Building and Construction Industry Security of Payment Act 1999 (Security of Payment Act).

Some of these changes are reversions to old systems, while others introduce completely new regimes. Readers will be forgiven for being irritated at yet another shock to the system, but it is vital to become familiar with all of these so that when they come into effect, businesses are ready for them. Directors and managers should take particular note as they will soon be open to criminal proceedings.

We wrote a pocket summary of these changes in December (see here).

Here we expand on the details, and we can now give some indication of when these changes will be activated.

Before going into the detail, readers should take note that as of 5 March 2019, none of these changes have come into effect.

When the changes will come in

This is the most important detail and so far, we don’t know. We will only know for sure after the fact, when the government makes the official announcement in the NSW Government Gazette.

However, a paper released by Fair Trading NSW in December 2018 has given some hints about when to expect these changes. It looks like there will be three main phases of changes throughout 2019 for principals and contractors to weather:

  • Phase 1 changes were proposed to come in during February 2019. This has not yet happened, so we can expect that any day now the changes will come;
  • Phase 2 changes were proposed for June 2019;
  • Phase 3 changes were schedule for December 2019.

When they do come into effect, they will not affect contracts already entered into. The old Security of Payment Act will still apply to these contracts.

Phase 1: February 2019

Investigation and enforcement powers for the Department

The most wide-reaching changes concern new powers of officers of the Department of Finance, Services and Innovation that can be used for the purposes of investigating, monitoring and enforcing compliance with the Security of Payment Act.

Authorised officers may now:

  • Require a person to provide them with information or records that they can obtain;
  • Require a person to answer questions on topics about which they are suspected of having knowledge, or to attend at a specified time and place to answer such questions;
  • Enter premises (including commercial premises without a search warrant);
  • When entering premises, make examinations, direct persons to produce records for examination, copy records, and seize anything suspected on reasonable grounds of being connected with an offence under the Security of Payment Act.

The Amendment Act also introduces offences for failing to comply with the above without reasonable excuse, or obstructing or delaying an authorised officer. The maximum penalty is $4,400 for a corporation and $2,200 for an individual.

There are even greater maximum penalties for providing information, answers or records that are false or misleading: $55,000 for a corporation and $11,000 for an individual.

Authorised officers will also be able to issue quick penalty notices for more minor infringements to the Security of Payment Act.

Liability of directors and managers

The Security of Payment Act already provides for offences of a corporation. See the next section for examples.

The Amendment Act now extends this liability to its directors, or for those involved in the management of the corporation (managers).

Where

  1. A corporation commits an offence against the Security of Payment Act, and
  2. A director or manager aids, abets, induces, conspires, is knowingly concerned in, or is a party to this offence,

then the director or manager will have committed an offence, which is subject to the same maximum penalty as applies to the corporation.

The Security of Payment Act also creates an “executive liability offence”. This is an offence involving specifically the supporting statement to a payment claim. These statements are required to be put forward by head contractors to certify that subcontractors have been paid.

Where:

  1. A corporation fails to attach a supporting statement to a payment claim, or the statement provided is false or misleading, and
  2. The director or manager knows this or is recklessly indifferent about it, and
  3. The director or manager has failed to take reasonable steps to prevent the offence.

the director or manager will have committed an executive liability offence. The maximum penalty is $22,000.

One example of failing to take reasonable steps under (3) is failing to ensure that a corporation’s employees, agents and contractors have supervision, and information and training about complying with the Security of Payment Act.

Higher penalties

Head contractors should take note that failure to include a supporting statement not only risks the payment claim to a principal being rendered invalid (which is the current law). Failure to include this is also now subject to tougher maximum penalties: $110,000 for corporations and $22,000 for individuals.

The same maximum penalties now apply where the supporting statement is provided by someone who knows that it contains false or misleading information. As mentioned, directors and managers may also be liable.

There are also offences relating to payment withholding requests. Currently a claimant in an adjudication application can issue a payment withholding request to the principal contractor, requiring them to hold back any money due to the respondent to cover a successful adjudication application. If a person receives this payment withholding request but is not, or is no longer, the principal contract, they must notify the claimant of this fact within 10 business days. The Amendment Act makes the penalties harsher: the maximum penalty for failing to do this is $5,500 for a corporation, and $1,100 for an individual.

There are similar increases in penalties where a claimant withdraws an adjudication application but fails to tell a principal who has received a payment withholding request, and where a respondent fails to comply with the direction by an adjudicator to give the identity and contact details of a principal contractor.

Adjudications reviewable for error

The Amendment Act now puts into writing what the courts have already decided. This is that an adjudicator’s determination, or any part of it, that is affected by jurisdictional error may be set aside by the Supreme Court. A jurisdictional error is where an adjudicator wrongfully decides a case that it has no authority to decide under the Security of Payment Act, such as where a payment claim is not properly served on the respondent or it is served without a supporting statement.

However, non-jurisdictional error, such as where an adjudicator makes a mistake about what the law is, is not reviewable.

No ball for companies in liquidation

A new change is that if a corporation claiming progress payments enters liquidation at any stage up until the final determination by an adjudicator, it will be prevented from claiming.

The NSW government is now denying the right of a corporation which is in liquidation to serve a payment claim, and is not allowing them to enforce a payment claim such as through applying for adjudication under the Security of Payment Act. This overrides some of a recent NSW Court of Appeal judgement.

A corporation that goes into liquidation while a determination is being considered is taken to have withdrawn the application.

There are uncertainties that NSW courts may need to resolve. Firstly, it appears that notwithstanding these changes, claimants in liquidation may still use the alternative to adjudication, which is enforcing a statutory debt that arises from unpaid payment schedules. Secondly, the Amendment Act does not appear to affect companies in voluntary administration. However, we may know for sure when the courts address these questions.

Phase 2: June 2019

Reference dates are no more

The Amendment Act removes the reference date system that has been the bane of many a claim.

It appears that the entitlement to a progress claim is no longer triggered by a reference date, but is merely triggered by that party undertaking to carry out construction work.

Under the new changes, contractors may serve a payment claim “on and from the last day” of the month in which work was carried out. If the contract provides for an earlier date of any month, the contractor may serve the payment claim from that date.

Only one payment claim per month

Unless the contract says otherwise, a claimant can only serve one payment claim in any particular month for work carried out in that month (previously one claim per reference date).

Parties can still include in a payment claim amounts that were the subject of previous payment claims, or include claims for work completed in previous months.

Payment claims after termination

Where a contract has been terminated, a contractor may serve a payment claim on or after the date of termination. This is a change from the existing law.

Endorsement of payment claims

In a return to the previous law, payment claims to be valid must state that they are “made under the Building and Construction Industry Security of Payment Act 1999”.

Shorter deadline for subcontractor payments

Where a party receives a payment claim from a subcontractor, the payment is due 20 business days after the payment claim is made (previously: 30 business days). If the contract provides for a shorter deadline, this shorter deadline will apply.

Withdrawal of an adjudication application

A claimant may now withdraw its adjudication application at any time before the application is determined. It can do this by serving written notice on both the respondent and the adjudicating body (and on the adjudicator, if one has been appointed).

Extended time for adjudicator’s decision

Under the original Security of Payment Act, the adjudicator must decide the application within 10 business days after notifying both parties that it has accepted the application.

The Amendment Act changes this where the respondent is entitled to lodge a response (e.g. where it had issued a payment schedule). The deadline for deciding the application is 10 business days after the respondent has lodged the response. If no response is lodged, the 10 business days start ticking at the end of the period that the respondent could have issued a response.

The adjudicator must now serve the determination on the claimant and the respondent.

Phase 3: December 2019

Owner-occupier exceptions removed

The Amendment Act makes changes so that the Security of Payment Act will apply to residential construction contracts between a builder and an owner-occupier of the building (that is, someone who resides or proposes to reside in the building).  Currently the Security of Payment Act does not apply to these contracts.

Codes of practice

The Minister for Innovation and Better Regulation may now prescribe a code of practice for adjudication bodies to follow. They will publish this on the NSW legislation website.

Bonus phase: May 2019

Lastly, Fair Trading NSW is also proposing changes to the Building and Construction Industry Security of Payment Regulation 2008 (Regulations).

These changes are scheduled to be drafted by May 2019, at which point stakeholders will be able to submit comments on these proposed changes.

  • Retention moneys for projects valued at over $20 million must currently be held in a trust account. It is proposed to reduce this threshold to $10 million, and to reduce annual reporting obligations on this trust account.
  • Fair Trading NSW proposes to amend the Regulations to require the keeping of trust account records by a head contractor, and to allow subcontractors to inspect these records if they have their retention held.
  • Liability of directors and managers of companies is proposed, for offences under the Regulations. These mainly relate to head contractors and trust accounts.

Conclusion

Fair Trading NSW has recommended that these changes be staggered over the course of a year to allow people in the industry to prepare for them. It is vital that everyone involved in construction and building business familiarise themselves with them. Even tiny non-compliances may have big consequences for adjudications. They can also give rise to criminal liability and severe penalties.

Businesses also need to be aware that authorised government officers will soon be perfectly within their rights to demand access to their documents and premises, and to demand answers to questions in relation to Security of Payment Act issues.

If you or someone you know wants more information or needs help or advice, please contact us on +61 (0)2 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-03-04 06:26:282019-04-08 07:13:47The Fantastic Fourth: another NSW Security of Payment amendment

Security of Payment – More Changes

November 2018/in Security of Payment

On 21 November 2018, the NSW government passed the Building and Construction Industry Security of Payment Amendment Act 2018.

This will make changes to the security of payment regime, and will take effect when the government announces so in the NSW Government Gazette.

So what are the main changes that builders and developers need to be aware of?

  • A payment claim must once again state that it is made under the Building and Construction Industry Security of Payment Act 1999 (“endorsement”);
  • Progress payments to a subcontractor are now due and payable 20 business days after a payment claim is issued (previously: 30 business days);
  • The ‘reference date’ system for payment claims is abolished. Now, where the contract is silent on dates for serving payment claims, a payment claim may be served on the last day of the month that construction work was first carried out under the contract, and then for the last day of each month of work afterwards;
  • Where a contract is terminated, a payment claim may be made from the date of termination;
  • If a head contractor company issues a payment claim to a principal and provides a supporting statement that is known to be false or misleading, then any company director who knows about this false or misleading statement can be convicted of an offence;
  • The Minister for Innovation and Better Regulation may make codes of practice to be observed by adjudicating organisations, and may cancel an adjudicating organisation’s authority for non-compliance with these;
  • Once a corporation is in liquidation, it cannot serve payment claims or enforce them;
  • Authorised officers from the Department of Finance, Services and Innovation now have extensive powers for the purposes of investigating, monitoring and enforcing compliance with the Act; and
  • Maximum penalties for various provisions have been increased.

The amendments also confirm what the High Court has already decided: that there are very limited grounds for appealing the decision of an adjudicator once it is made.

Other changes have also been made. These changes do not apply to any contract entered into before the amendments take effect. If you’d like to know more, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-11-27 22:13:552018-11-28 04:46:08Security of Payment – More Changes

Challenging Adjudication Determinations – some recent guidance

September 2018/in Security of Payment

Parties to a commercial building dispute may utilise Security of Payment (SOP) legislation in their jurisdiction to resolve payment claims and recover money owing under a construction contract.

Disputes are resolved quickly by an adjudicator and any amount determined as owing must be paid within the statutory timeframe. The determination is enforceable but without prejudice to the common law rights of either party. Due to the limited time in which an adjudicator must determine a payment dispute, it is not surprising that a determination may come before the Court for judicial review.

The grounds for review have been visited by various Courts with the following cases providing insight as to what might (and might not) justify having an adjudication determination quashed.

No review avenues for non-jurisdictional error

The High Court in Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4 confirmed that parties to an adjudication determination under the Building and Construction Security of Payment Act 1999 (NSW) may not seek judicial review for non-jurisdictional error of law.

The Court reiterated the nature of the (NSW) Act which, amongst other things, was intended to ‘reform payment behaviour in the construction industry’ by ensuring prompt recovery of payment for work carried out under a construction contract. The legislation is ‘coherent, expeditious and self-contained’ and ‘not concerned with finally and conclusively determining the entitlements of parties to a construction contract’.

Accordingly, an adjudicator is sanctioned to make a determination and a Court is not empowered to quash that decision for non-jurisdictional error, even if based on an incorrect interpretation of the subject contract.

An adjudication determination may only be set aside on grounds of jurisdictional error – an error going to the authority or power of the adjudicator, such as non-compliance with procedural requirements under SOP legislation.

Minimum standards required when assessing an adjudication determination

Nuance Group (Australia) Pty Limited (Nuance) v Shape Australia Pty Limited (Shape)[2018] VSC 362 provides guidance as to when a Court might quash an adjudication determination.

Shape served a payment claim on Nuance for over $3.5 million for demolition and associated works at Melbourne International Airport. Nuance responded with a payment schedule stating the amount payable as nil. Shape applied for adjudication for the sum of $2,243,105.55. An amount of $1,400,007.12 was determined payable, which after an adjudication review instigated by Nuance, was reduced to $1,216,715.72.

Nuance challenged the validity of both the original and reviewed determination in the Supreme Court of Victoria.

Nuance submitted that the adjudicator had not determined the amount of the progress claim as required by SOP legislation, which as a minimum necessitated a finding of whether the work identified in the relevant claim had in fact been performed and the value of that work. Rather, the adjudicator had deducted what he considered were excluded amounts from Shape’s claim to arrive at the revised figure and, in doing so, failed to comply with ‘basic and essential requirements’ of the Act.

Nuance was successful, and the adjudication determination was quashed.

Whilst acknowledging the tight timeframes under which adjudicators are required to operate, Justice Digby nonetheless conceded that the adjudicator had:

‘…failed to undertake the required task of addressing the payment claim and payment schedule and, consider those parameters of the dispute between the claimant and the respondent as to what claimed work … had been carried out under the Contract and what the value of that work … was.’

The adjudicator had merely worked back from the original claim in a manner that did not constitute a ‘fair and reasonable consideration’ of the determination providing ‘no sufficiently comprehensible reasons and basis for the amount determined’.

An adjudicator’s reasons must be considered in context

Southern Cross Electrical Engineering (Southern Cross) v Steve Magill Earthmoving (Magill) [2018] NSWSC 1027 considered another appeal of an adjudication decision.

Essentially, Southern Cross disputed Magill’s payment claim, which comprised additional amounts for excavation work based on trenching some areas of the subject site that were wider than stipulated in the contract. Southern Cross submitted that the adjudicator had erred by requiring it to prove that there had been no variation to the contract and that the earthmoving works had been over-claimed.

Relying on Justice Vickery’s lengthy series of matters to consider in Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631, Southern Cross claimed that the adjudicator was required to ‘examine all the material for himself, and to come to a conclusion, based on that material as to what amount (if any) is payable.’

Justice McDougall acknowledged the processes set out by Justice Vickery were applicableto a determination however rejected any requirement for them to be ‘applied serially and mechanically in every case.’ Rather, the adjudicator’s reasons must be considered in context which included ‘the content of the dispute as established by the payment claim and the payment schedule, and the parties’ elaboration of that dispute.’

Further, the reasoning must be assessed considering the interim nature of an adjudicator’s determination under SOP legislation, the voluminous material to be dealt with, the strict timeframe and the fact that adjudicators are not usually lawyers.

Cross Engineering’s appeal was dismissed, Justice McDougall concluding that:

‘Factually, the adjudicator’s approach may have been (and probably was) incorrect. It is no doubt something that could have been improved upon if the adjudicator had “world enough and time”. But looking at his approach … I am far from persuaded that it was unreasonable to the extent that it must be taken to invalidate his determination’.

Conclusion

An adjudication determination is not subject to judicial review for non-jurisdictional error.

An adjudicator must apply certain minimum standards when assessing an adjudication application, however his or her reasoning will be considered in the context of the purpose and intent of the legislation, that being for the timely resolution of payment disputes under a construction contract. A decision that emanates from an error of law not associated with a jurisdictional error, will generally not entitle the Court to intervene.

Security of Payments legislation across Australia has been the subject of review and proposed reform. The recent release of the Murray Report recommends the national harmonisation of SOP laws and the implementation of review rights for parties (by a review adjudicator) for determinations concerning amounts of $100,000 or more.

If implemented, construction industry participants should have greater clarity regarding the circumstances under which an aggrieved party can challenge an adjudication determination.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-09-18 15:25:082018-09-19 07:27:48Challenging Adjudication Determinations – some recent guidance

When adjudication certificates meet statutory demands

July 2018/in Security of Payment

Parties to a payment dispute in the commercial building industry may utilise the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘SOPA’) to resolve the matter.

The Act provides an efficient means of recovering money owed for construction work by invoking a statutory right for a contractor to receive progress payments under a contract.

Disputes are usually resolved quickly by an adjudicator. A determination is made which, in most cases, requires a respondent to pay the claimant a specified amount within the statutory timeframe. The determination is enforceable but without prejudice to the common law rights of either party. If the respondent fails to pay, the claimant may apply for an adjudication certificate which can be filed in Court to obtain judgement against the respondent.

When additional attempts are made under other legislation to enforce payment of the debt the matter can become complex.

Powerpark Systems Pty Ltd [2018] NSWSC 793 considers the interplay between the state-based SOPA and the issue of a statutory demand under the Commonwealth’s Corporations Act 2001. The case recognises the policy supporting the adjudication process and emphasises the need for parties to act quickly if they wish to challenge a determination.

The case and the decision

Powerpark Pty Ltd (Powerpark) retained Shoemark Electrical Pty Ltd (Shoemark) to install solar panels at various sites. Shoemark invoiced Powerpark for $44,811.11 for services carried out in New South Wales and Queensland and subsequently issued a payment claim under the SOPA.

Powerpark responded to the claim by issuing a payment schedule complaining of Shoemark’s defective work at building sites, agreeing to pay $24,956.97, and threatening to pursue Shoemark for rectification costs if the defective work was not resolved.

Shoemark proceeded to have the claim adjudicated which was determined in its favour for $44,811.11. Relying on the adjudication certificate, Shoemark served a statutory demand on Powerpark under the Corporations Act 2001. (The effect of serving a statutory demand is that a company will be presumed insolvent if, after 21 days it fails to pay the debt or is unsuccessful in having the demand set aside by a Court.)

Subsequently, and pursuant to the SOPA, Shoemark obtained judgment against Powerpark from the Local Court for $48,230.74 being the amount determined under adjudication plus fees and interest.

Powerpark applied to the Supreme Court to have the statutory demand set aside on the following grounds:

  • There was a genuine dispute about the existence or amount of the debt due to a purported jurisdictional error affecting the adjudication certificate and judgment.

One of the contracts for which the adjudication was determined related to work performed in Queensland. Powerpark claimed that as the SOPA expressly excluded work performed outside of New South Wales, the adjudication was ‘beyond the jurisdiction of the adjudicator’. It followed that the judgement issued by the Local Court in reliance of the adjudication certificate should be void.

The Court rejected this argument. Although the SOPA does not apply to work performed outside of New South Wales that in itself, was insufficient to invalidate the judgement. Whilst a potentially erroneous decision is reviewable, once the adjudication certificate is filed the debt is nevertheless payable.

Although Powerpark may have applied for judicial review to stay the judgement for jurisdictional error, its’ time for commencing proceedings had expired and it failed to explain any reason for not commencing or delaying proceedings.

  • The jurisdictional error constituted ‘some other reason’ as to why the demand should be set aside in accordance with s 459(1)(b) of the Corporations Act 2001.

Powerpark was again unsuccessful on this argument. The Court has discretion regarding what may constitute ‘some other reason’ to have a statutory demand set aside however, ‘the pendency of curial proceedings’ was, without more, insufficient to establish ‘some other reason.’

  • Powerpark had an offsetting claim against Shoemark comprising the losses claimed due to defective work.

On this point Powerpark was again unsuccessful in having the statutory demand set aside. It did however convince the Court of its offsetting claim resulting in the amount of the statutory demand being reduced to $21,483.14 which took into account the defective works.

Key takeaways

  • A judgment arising from the filing of an adjudication certificate determines that the judgment debt is indisputably due and payable. The legislative policy supporting the SOPA is to facilitate payment of an adjudicated amount notwithstanding the potential of a ‘curial dispute’ which, if later established could be cured by restitution.
  • An offsetting claim (in respect of a statutory demand) may be ordered by a Court without disturbing the validity of an adjudication certificate or the statutory demand.
  • Once a judgment debt issues, the subject of an adjudication certificate, a respondent will face difficulties in challenging its validity. Obtaining early advice during any construction payment dispute is important to ensure the merits of the proceedings and relevant timeframes are considered.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-07-10 09:59:532019-06-20 23:43:26When adjudication certificates meet statutory demands

National review of security of payment legislation by John Murray AM

June 2018/in Security of Payment

The long-awaited national review of security of payment legislation by John Murray AM has been released.

The ‘Murray Report’ recommends harmonised security of payment laws across Australia by selecting various provisions of each state’s and territory’s model and emphasises the importance of the Commonwealth, states and territories working together to implement those recommendations.

Some of the key recommendations of the Murray Report:

  1. Reference dates to be replaced with an entitlement to make a payment claim every named month, or more frequently if so provided under the contract;
  1. Payment claims to identify a detailed breakdown of the amount claimed; the time period within which the respondent is to provide a payment schedule; and should be endorsed as a claim made under the legislation (among other related requirements);
  1. Supporting statements to accompany payment claims submitted to a head contractor to the principal (requiring a statement that subcontractors and suppliers have been paid);
  1. All adjudicators are to be trained, registered, graded and appointed to disputes by a new regulator;
  1. The introduction of statutory trusts for subcontractor payment and the adoption of an extended Christmas shutdown period; and
  1. Any parts of an adjudicator’s decision that falls into jurisdictional error, but does not affect the whole of the decision, can be severed;
  1. Claimants to be entitled to withdraw and make a new application if an adjudicator has not accepted its application within 4 business days, an adjudicator fails to determine an application within the prescribed timeframe or an adjudicator has given notice of their withdrawal from the adjudication;
  1. Parties entitled to make an application for a review of an adjudication determination if the adjudicated amount is equal to or greater than $100,000 of the scheduled amount, or $100,000 (or more) lower than the claimed amount.

The Australian Government is working with the states and territories through the Building Ministers’ Forum (BMF) to consider and respond to the findings and recommendations of the Murray Report.  Responsibility for this project has now transferred to the Department of Industry, Innovation and Science which provides secretariat support to the BMF.

We will keep you posted on developments and look forward to the proposed harmonisation of security of payment legislation.

Regards Brendan and Scott

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-06-15 13:46:122018-08-17 14:40:05National review of security of payment legislation by John Murray AM

No notice needed: NSW Court of Appeal rules on enforcement of Security of Payment Act determination

March 2017/in Security of Payment

In the recent unanimous decision of Fitz Jersey Pty Ltd v Atlas Construction Group Pty Ltd [2017] NSWCA 53, the Court of Appeal considered the enforcement of a judgment (pursuant to an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act)) by garnishee order and without notice of the judgment being given to the unsuccessful respondent.

The Court of Appeal confirmed:

  • the long-held view that notice of the entry of and enforcement of a judgment (obtained pursuant to an adjudication determination) is not required; and
  • that, when applying for a garnishee order, a party is not required to disclose to the Court that an unsuccessful respondent to an adjudication determination has commenced proceedings challenging the adjudication determination underlying the judgment (unless there are special circumstances, such as a stay or undertaking has been sought).

Background

The background to the Court of Appeal’s decision can be briefly summarised as follows.

1. On 6 January 2017, an adjudicator determined an adjudication application in favour of the builder in the amount of $10,748,466.31 plus interest and the adjudicator’s fees.

2. On 13 January 2017, the developer was required to pay to the builder the adjudicated amount plus interest and the adjudicator’s fees in accordance with section 23 of the Act.

3. On 13 January 2017, the developer did not pay the adjudicated amount to the builder.  Instead, the developer filed and served a Summons and List Statement in the Technology and Construction List of the Supreme Court of NSW seeking an order that the adjudication determination be quashed.  The letter to the builder’s solicitor serving the Summons and List Statement relevantly said:

“We are instructed that if your client seeks an order at that directions hearing that our client lodge the amount of the adjudication determination with the Supreme Court until a judgment is issued on our client’s summons, our client will not object to that order being made.” 

4. On 16 January 2017, the builder requested an adjudication certificate for the adjudicated amount and the amounts for interest and the adjudicator’s fees.

5. On 17 January 2017, the builder received the adjudication certificate in the amount of $11,023,619.76 and filed the certificate as a judgment of the Supreme Court.  Later, on 17 January 2017, the builder applied for a garnishee order against NAB in respect of the judgment amount.

6. On 27 January 2017, the Supreme Court issued the garnishee order against NAB for the amount of the judgment debt.  Later, on 27 January 2017, the garnishee order was served on NAB.

7. On 2 February 2017, NAB paid the full amount of the judgment debt to the builder.

8. On 3 February 2017, the developer became aware of the judgment, the garnishee order and the payment by NAB.

Supreme Court application

On 6 February 2017, the developer made an application to the Supreme Court seeking orders that the amount paid pursuant to the garnishee order be repaid into Court.  The developer’s application was based on two grounds.

  1. The developer primarily submitted that, because the developer did not have notice of the builder’s application for an adjudication certificate or the entry of judgment, the developer had been deprived of an alleged entitlement or right under section 25 of the Act to pay the money into Court pending the determination of the validity of the determination.
  2. The developer also relied on a secondary argument that the proceedings commenced by the developer to have the adjudication determination quashed should have been disclosed in the builder’s application for a garnishee order.

The Supreme Court dismissed the application.  The Court did not consider it appropriate to deal with the developer’s argument under section 25 of the Act on an urgent application and said that it did not consider that an applicant for a garnishee order needed to put any additional material before the Court (other than as required by the Uniform Civil Procedure Rules 2005 (NSW) (Rules), which prescribes the form and requirements for an application for a garnishee order).

In any event, at a more fundamental level, the Court cited the developer’s failure to obtain an injunction or seek an undertaking restraining the enforcement of the adjudication determination as reasons why the Court would not exercise its discretion to grant the equitable relief sought by the developer.

Court of Appeal decision

The developer appealed the Supreme Court’s decision on three grounds, the first of which was essential for the other grounds to succeed.

  1. The Supreme Court incorrectly exercised its discretion in refusing equitable relief.
  2. The builder was required to notify the developer that a judgment had been obtained before taking steps to enforce it.
  3. When applying for a garnishee order, the builder was required to notify the Court that the developer had commenced proceedings to review the underlying adjudication determination.

Is there an obligation to notify of a judgment pursuant to an adjudication determination before enforcement?

In short, no.  The Court of Appeal considered section 25 of the Act, in conjunction with the Rules in respect of the entry and enforcement of judgments.

Relevantly, section 25 of the Act provides as follows.

“25   Filing of adjudication certificate as judgment debt

(1)       An adjudication certificate may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly.

(2)       An adjudication certificate cannot be filed under this section unless it is accompanied by an affidavit by the claimant stating that the whole or any part of the adjudicated amount has not been paid at the time the certificate is filed.

(3)       If the affidavit indicates that part of the adjudicated amount has been paid, the judgment is for the unpaid part of that amount only.

(4)       If the respondent commences proceedings to have the judgment set aside, the respondent:

(a)       is not, in those proceedings, entitled:

(i)        to bring any cross-claim against the claimant, or

(ii)       to raise any defence in relation to matters arising under the construction contract, or

(iii)      to challenge the adjudicator’s determination, and

(b)       is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.”

For various reasons, including those noted below, the Court found that there is no obligation on a party that registers an adjudication certificate as a judgment to notify the other party that a judgment has been entered.

  • Rule 36.14 of the Rules provides that a judgment need not be served unless expressly required by the Rules.  The Rules were introduced after the operation of the Act.  There is no express requirement in the Act or the Rules that a judgment must be served or notified to the other party.
  • The proposition that a judgment cannot be enforced without service on the other party “has no support in authority, or as a matter of general principle.  It would, on its face, be inconsistent with the proposition that service is not required”, as per Rule 36.14 (as noted above).
  • Section 25(4) of the Act does not put the unsuccessful party in a better position than any other judgment debtor (upon which service of a judgment is not required before enforcement).  The effect of section 25(4) on an unsuccessful respondent to an adjudication determination is restrictive.
  • Section 25(4)(b) of the Act operates to require payment into Court of the unpaid portion of the adjudicated amount, if any (pending the determination by the Court of whether or not the judgment should be set aside).  It does not require there to be an unpaid portion.
  • To require notice of the existence of a judgment would deny the effect of the words “enforceable accordingly” in section 25(1) of the Act: “There is no authority which seeks to adopt such a construction, nor does it fit with either the context in which s 25(1) appears, the objects of the Act, or anything in the legislative history.”

Interestingly, the Court of Appeal was at pains to clarify that section 25(4) of the Act does not confer any right to have a judgment set aside.  The Court’s power to set aside a judgment is founded in the Rules and in the inherent jurisdiction of the Court.

Further, the Court said that section 25(4)(b) of the Act, which requires the adjudicated amount to be paid into Court pending the Court’s determination of an application to set aside a judgment based on an adjudication determination, would not apply to an application to quash a determination before judgment has been entered (although, in practice, the Courts have required payment into Court of the adjudicated amount pending the determination of the challenge to the validity of the determination, by analogy to section 25(4)(b) of the Act).

Is there an obligation to disclose a challenge to an adjudication determination when applying for a garnishee order?

In short, no.  However, there may be circumstances where additional disclosure is required in an application for a garnishee order (or other ex parte application).  The extent of such disclosure will depend on the facts of the case and may include, for example, if an undertaking not to enforce has been sought and an application to seek a stay has been foreshadowed.

The Court of Appeal found, amongst other things.

  • The statutory context of an application for a garnishee order to enforce an adjudication under the Act is critical.  The payments under the Act are interim in nature (subject to final determination as contemplated by section 32 of the Act) and any reduction in the entitlement of a builder to enforce an adjudication determination would undermine the statutory purpose of the Act.  The fact that the judgment is interim and subject to a further final determination (as contemplated by section 32 of the Act) lessens the obligation of disclosure.
  • As per the Rules, an application for a garnishee order may be dealt with in the absence of the parties and need not be served on the judgment debtor or the proposed garnishee.  That accords with public policy reasons that judgment debtors should not be notified so that they do not take steps to avoid payment, e.g. transferring assets.
  • The question which must ultimately be determined is whether any fact disclosed would have been likely to affect the outcome of the application – otherwise setting an order aside is “an entirely penal exercise, which must be proportionate to the consequences for the party in breach”.
  • Therefore, the onus was on the developer to establish that the builder should be deprived of an entitlement to immediate payment of the determined amount on an interim basis, i.e. the developer needed to demonstrate reasonable prospects of success on its application for judicial review and that it may not be possible to recover the money from the builder, neither of which had been established by the developer in this case.

What does this mean for me?

1. If you are successful in an adjudication determination:

(a) judgment can be obtained by registering an adjudication certificate and there is no need to notify the respondent to the adjudication determination, even if the respondent has commenced proceedings to challenge the validity of the adjudication determination; and

(b) the judgment may be enforced by garnishee order and the extent to which an application for a garnishee order must disclose a challenge to the validity of the determination will depend on the steps taken by the unsuccessful respondent.  If the respondent has merely commenced proceedings challenging the determination (and not sought an undertaking or an injunction), no disclosure is required.

2. If you are unsuccessful in an adjudication determination and do not intend to pay the adjudicated amount by the time prescribed in the Act, you should seek an undertaking from the successful party that it will not enforce the determination until the Court rules on the validity of the determination.  If no undertaking is provided, an urgent injunction should be sought.

CONTACT US

Ground Floor
437 Kent Street
Sydney NSW 2000
 +612 9248 3450
info@bradburylegal.com.au

FLEXIBLE APPROACH & FEE OPTIONS

We will set up fee structures that ensure you are only charged when we add value and not each time you pick up the phone or send an email.

If you don’t want to pay hourly rates, then don’t.

Ask us about our fixed fees and retainers.

https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://secureservercdn.net/50.62.88.87/g6u.f01.myftpupload.com/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-03-30 06:54:052018-08-20 06:55:50No notice needed: NSW Court of Appeal rules on enforcement of Security of Payment Act determination
Page 3 of 512345

Categories

  • Commercial Issues
  • Construction Regulation
  • Contract Issues
  • Disputes
  • Security of Payment
  • Uncategorized

Archive

  • March 2022
  • February 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • February 2021
  • January 2021
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • November 2019
  • September 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • January 2019
  • November 2018
  • October 2018
  • September 2018
  • July 2018
  • June 2018
  • April 2018
  • March 2017
  • January 2017
  • December 2016
  • October 2016
  • June 2016
  • May 2016
  • April 2016
  • February 2016
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • April 2015
  • March 2015
  • February 2015
  • October 2014

Our Address

Ground Floor, 437 Kent Street,
Sydney NSW 2000
02 9030 7400  |  info@bradburylegal.com.au

About Bradbury Legal

We are a boutique law firm providing high quality, personalised legal services to the property, development and construction industries.

Liability limited by a scheme approved under Professional Standards Legislation © Copyright - Bradbury Legal
  • LinkedIn
  • Mail
  • Instagram
  • Facebook
Scroll to top