Bradbury Legal
  • Home
  • Services
    • Contract Drafting & Negotiation
    • Corporate & Commercial Advice
    • Dispute Resolution
    • Project Management & Contract Administration
    • Property Development Advice
    • Security of Payment
  • Our People
  • Updates
  • Contact
  • Privacy Policy
  • Menu Menu
  • LinkedIn
  • Mail
  • Instagram
  • Facebook

Does a payment claim survive the termination of a contract for convenience?

May 2019/in Security of Payment

Security of payment legislation continues to receive significant attention across Australia’s building and construction landscape, with many cases being deconstructed to shed light on a court’s interpretation of various provisions.

Impero Pacific Group Pty Ltd v Bonheur Holdings Pty Ltd [2019] NSWSC 286 recently established that, despite a construction contract being terminated for convenience, a contractor may still claim for work carried out between the last accrued reference date and the termination date. Much will depend on the wording of the contract.

The decision diverges from previous case law which holds that a contract terminated for convenience does not provide ongoing reference dates, and consequently no entitlement for a contractor to claim for work carried out between the last reference date and termination.

Background

The contractor, Impero Pacific Group Pty Ltd (Impero) entered into a contract with Bonheur Holdings Pty Ltd (Bonheur), as principal, for construction of a residential strata complex, with a completion date of 1 March 2019.

The reference date, for the purposes of making payment claims was the 25th day of the month.

Crucially, the contract contained a termination for convenience clause (clause 39A), allowing the principal at its discretion to terminate the contract and complete any part of the works either itself or through another party. If invoked, the contractor would be entitled to payment for certain works carried out to the date of termination that would otherwise have been payable if the contract had not been terminated.

The contract was terminated for convenience by Bonheur on 29 or 30 October 2018.

Impero served a payment claim on 27 November 2018 for approximately $1.4 million relating to work undertaken between the last reference date being 25 October 2018 and the termination date, namely 29 or 30 October 2018.

Bonheur failed to respond to the claim as required under the Act and Impero sought judgement from the Supreme Court.

Bonheur argued that the payment claim was invalid as it was not supported by an available reference date pursuant to clause 8 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘Act’).  It contended that if the contract was terminated for convenience, “the Act cannot be used to obtain a progress payment for work done between the last contractual progress payment date and the date of termination.”

It was also submitted that, if Impero did have a right to a progress payment, it was “limited to part only” on the basis that it had claimed for items not within the scope of the Act and therefore no judgement could be obtained.

Impero argued that on construction of clause 39A, termination resulted in the creation of a new reference date and a consequential entitlement to claim and receive payment.

Decision

Justice Parker was not persuaded by the principal’s submissions and ordered the judgement sought by Impero.

The Act provides that on and from each reference date under a construction contract a person is entitled to a progress payment for work carried out under the contract.

Justice Parker acknowledged that under the current Act “there is no entitlement to a progress payment, and there can be no valid progress claim, unless there is an available reference date”. A reference date is defined as:

“(a)    a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out…under the contract, or

(b)     if the contract makes no express provision with respect to the matter – the last day of the named month in which the construction work was first carried out…and the last day of each subsequent named month.“

The last reference date prior to termination (on 29 or 30 October) was 25 October, which would have been available to claim for work carried out up to that date, but not beyond. Had the contract not been terminated, the next available reference date would have been 25 November.

Justice Parker considered the present matter in the context of previous cases and clause 39A of the construction contract. Clause 39A provided an entitlement for Impero to claim for work carried out under the contract up to the date of termination, and crucially this clause expressly stated that it would survive termination.

In the circumstances it was determined that “termination of the contract gave rise to a fresh reference date for the purposes of the Act“ and the entitlement for Impero to claim up to termination.

As to the contention that Impero’s right to a progress payment, if awarded, should be limited to part only, Justice Parker confirmed that “the Act does not permit the Court to make its own assessment of the extent to which the claimed amount represents payment for construction work or the supply of related goods or services. In that sense, it is an all-or-nothing provision.” The opportunity for a principal to argue that items fall beyond the scope of the Act arises by serving a payment schedule in response to a contractor’s payment claim. In the present case, the principal failed to do this.

Key takeaways

  • The exercise of a right to terminate a construction contract for convenience will not prevent a contractor from claiming for work carried out up to the termination date;
  • Progress claims should specify the works carried out between the last accrued reference date and the date of termination and relate only to works defined within the scope of the Act; and
  • Principals who terminate a contract for convenience should anticipate that a contractor may make a claim up to the date of termination. Items considered to be claims beyond the scope of the Act should be identified in the payment schedule.

Readers should be aware that Justice Parker makes it clear that termination for convenience is not the same as termination for breach nor is it similar to accepting the repudiation of the other party. The situation may be different in these cases. The High Court of Australia has previously ruled that in these cases, unless the contract expressly provides so, reference dates do not accrue after termination or accepted repudiation.

Where to next?

Determinations such as this are frequently analysed, particularly as participants in the building and construction industry await reforms yet to commence under the Building and Construction Industry Security of Payment Amendment Act 2018 (NSW). For more details on these amendments, click here.

Upon commencement of the current reforms proposed, the reference date system will be abolished, and a contractor will be able to make a progress claim for work carried out up to the date of a terminated contract, whether the contract is terminated for convenience or otherwise.

The policy behind these amendments is to discourage principals from strategically terminating a contract primarily to avoid a final payment claim being made under the Act.

If you or someone you know wants more information or needs help or advice, please contact us on +61 2 9248 3450 or email info@bradburylegal.com.au.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-05-14 22:43:302019-05-14 23:45:28Does a payment claim survive the termination of a contract for convenience?

The Fantastic Fourth: another NSW Security of Payment amendment

March 2019/in Security of Payment

On 21 November 2018, the NSW Houses of Parliament passed the Building and Construction Industry Security of Payment Amendment Act 2018 (Amendment Act). This will amend some provisions of the Building and Construction Industry Security of Payment Act 1999 (Security of Payment Act).

Some of these changes are reversions to old systems, while others introduce completely new regimes. Readers will be forgiven for being irritated at yet another shock to the system, but it is vital to become familiar with all of these so that when they come into effect, businesses are ready for them. Directors and managers should take particular note as they will soon be open to criminal proceedings.

We wrote a pocket summary of these changes in December (see here).

Here we expand on the details, and we can now give some indication of when these changes will be activated.

Before going into the detail, readers should take note that as of 5 March 2019, none of these changes have come into effect.

When the changes will come in

This is the most important detail and so far, we don’t know. We will only know for sure after the fact, when the government makes the official announcement in the NSW Government Gazette.

However, a paper released by Fair Trading NSW in December 2018 has given some hints about when to expect these changes. It looks like there will be three main phases of changes throughout 2019 for principals and contractors to weather:

  • Phase 1 changes were proposed to come in during February 2019. This has not yet happened, so we can expect that any day now the changes will come;
  • Phase 2 changes were proposed for June 2019;
  • Phase 3 changes were schedule for December 2019.

When they do come into effect, they will not affect contracts already entered into. The old Security of Payment Act will still apply to these contracts.

Phase 1: February 2019

Investigation and enforcement powers for the Department

The most wide-reaching changes concern new powers of officers of the Department of Finance, Services and Innovation that can be used for the purposes of investigating, monitoring and enforcing compliance with the Security of Payment Act.

Authorised officers may now:

  • Require a person to provide them with information or records that they can obtain;
  • Require a person to answer questions on topics about which they are suspected of having knowledge, or to attend at a specified time and place to answer such questions;
  • Enter premises (including commercial premises without a search warrant);
  • When entering premises, make examinations, direct persons to produce records for examination, copy records, and seize anything suspected on reasonable grounds of being connected with an offence under the Security of Payment Act.

The Amendment Act also introduces offences for failing to comply with the above without reasonable excuse, or obstructing or delaying an authorised officer. The maximum penalty is $4,400 for a corporation and $2,200 for an individual.

There are even greater maximum penalties for providing information, answers or records that are false or misleading: $55,000 for a corporation and $11,000 for an individual.

Authorised officers will also be able to issue quick penalty notices for more minor infringements to the Security of Payment Act.

Liability of directors and managers

The Security of Payment Act already provides for offences of a corporation. See the next section for examples.

The Amendment Act now extends this liability to its directors, or for those involved in the management of the corporation (managers).

Where

  1. A corporation commits an offence against the Security of Payment Act, and
  2. A director or manager aids, abets, induces, conspires, is knowingly concerned in, or is a party to this offence,

then the director or manager will have committed an offence, which is subject to the same maximum penalty as applies to the corporation.

The Security of Payment Act also creates an “executive liability offence”. This is an offence involving specifically the supporting statement to a payment claim. These statements are required to be put forward by head contractors to certify that subcontractors have been paid.

Where:

  1. A corporation fails to attach a supporting statement to a payment claim, or the statement provided is false or misleading, and
  2. The director or manager knows this or is recklessly indifferent about it, and
  3. The director or manager has failed to take reasonable steps to prevent the offence.

the director or manager will have committed an executive liability offence. The maximum penalty is $22,000.

One example of failing to take reasonable steps under (3) is failing to ensure that a corporation’s employees, agents and contractors have supervision, and information and training about complying with the Security of Payment Act.

Higher penalties

Head contractors should take note that failure to include a supporting statement not only risks the payment claim to a principal being rendered invalid (which is the current law). Failure to include this is also now subject to tougher maximum penalties: $110,000 for corporations and $22,000 for individuals.

The same maximum penalties now apply where the supporting statement is provided by someone who knows that it contains false or misleading information. As mentioned, directors and managers may also be liable.

There are also offences relating to payment withholding requests. Currently a claimant in an adjudication application can issue a payment withholding request to the principal contractor, requiring them to hold back any money due to the respondent to cover a successful adjudication application. If a person receives this payment withholding request but is not, or is no longer, the principal contract, they must notify the claimant of this fact within 10 business days. The Amendment Act makes the penalties harsher: the maximum penalty for failing to do this is $5,500 for a corporation, and $1,100 for an individual.

There are similar increases in penalties where a claimant withdraws an adjudication application but fails to tell a principal who has received a payment withholding request, and where a respondent fails to comply with the direction by an adjudicator to give the identity and contact details of a principal contractor.

Adjudications reviewable for error

The Amendment Act now puts into writing what the courts have already decided. This is that an adjudicator’s determination, or any part of it, that is affected by jurisdictional error may be set aside by the Supreme Court. A jurisdictional error is where an adjudicator wrongfully decides a case that it has no authority to decide under the Security of Payment Act, such as where a payment claim is not properly served on the respondent or it is served without a supporting statement.

However, non-jurisdictional error, such as where an adjudicator makes a mistake about what the law is, is not reviewable.

No ball for companies in liquidation

A new change is that if a corporation claiming progress payments enters liquidation at any stage up until the final determination by an adjudicator, it will be prevented from claiming.

The NSW government is now denying the right of a corporation which is in liquidation to serve a payment claim, and is not allowing them to enforce a payment claim such as through applying for adjudication under the Security of Payment Act. This overrides some of a recent NSW Court of Appeal judgement.

A corporation that goes into liquidation while a determination is being considered is taken to have withdrawn the application.

There are uncertainties that NSW courts may need to resolve. Firstly, it appears that notwithstanding these changes, claimants in liquidation may still use the alternative to adjudication, which is enforcing a statutory debt that arises from unpaid payment schedules. Secondly, the Amendment Act does not appear to affect companies in voluntary administration. However, we may know for sure when the courts address these questions.

Phase 2: June 2019

Reference dates are no more

The Amendment Act removes the reference date system that has been the bane of many a claim.

It appears that the entitlement to a progress claim is no longer triggered by a reference date, but is merely triggered by that party undertaking to carry out construction work.

Under the new changes, contractors may serve a payment claim “on and from the last day” of the month in which work was carried out. If the contract provides for an earlier date of any month, the contractor may serve the payment claim from that date.

Only one payment claim per month

Unless the contract says otherwise, a claimant can only serve one payment claim in any particular month for work carried out in that month (previously one claim per reference date).

Parties can still include in a payment claim amounts that were the subject of previous payment claims, or include claims for work completed in previous months.

Payment claims after termination

Where a contract has been terminated, a contractor may serve a payment claim on or after the date of termination. This is a change from the existing law.

Endorsement of payment claims

In a return to the previous law, payment claims to be valid must state that they are “made under the Building and Construction Industry Security of Payment Act 1999”.

Shorter deadline for subcontractor payments

Where a party receives a payment claim from a subcontractor, the payment is due 20 business days after the payment claim is made (previously: 30 business days). If the contract provides for a shorter deadline, this shorter deadline will apply.

Withdrawal of an adjudication application

A claimant may now withdraw its adjudication application at any time before the application is determined. It can do this by serving written notice on both the respondent and the adjudicating body (and on the adjudicator, if one has been appointed).

Extended time for adjudicator’s decision

Under the original Security of Payment Act, the adjudicator must decide the application within 10 business days after notifying both parties that it has accepted the application.

The Amendment Act changes this where the respondent is entitled to lodge a response (e.g. where it had issued a payment schedule). The deadline for deciding the application is 10 business days after the respondent has lodged the response. If no response is lodged, the 10 business days start ticking at the end of the period that the respondent could have issued a response.

The adjudicator must now serve the determination on the claimant and the respondent.

Phase 3: December 2019

Owner-occupier exceptions removed

The Amendment Act makes changes so that the Security of Payment Act will apply to residential construction contracts between a builder and an owner-occupier of the building (that is, someone who resides or proposes to reside in the building).  Currently the Security of Payment Act does not apply to these contracts.

Codes of practice

The Minister for Innovation and Better Regulation may now prescribe a code of practice for adjudication bodies to follow. They will publish this on the NSW legislation website.

Bonus phase: May 2019

Lastly, Fair Trading NSW is also proposing changes to the Building and Construction Industry Security of Payment Regulation 2008 (Regulations).

These changes are scheduled to be drafted by May 2019, at which point stakeholders will be able to submit comments on these proposed changes.

  • Retention moneys for projects valued at over $20 million must currently be held in a trust account. It is proposed to reduce this threshold to $10 million, and to reduce annual reporting obligations on this trust account.
  • Fair Trading NSW proposes to amend the Regulations to require the keeping of trust account records by a head contractor, and to allow subcontractors to inspect these records if they have their retention held.
  • Liability of directors and managers of companies is proposed, for offences under the Regulations. These mainly relate to head contractors and trust accounts.

Conclusion

Fair Trading NSW has recommended that these changes be staggered over the course of a year to allow people in the industry to prepare for them. It is vital that everyone involved in construction and building business familiarise themselves with them. Even tiny non-compliances may have big consequences for adjudications. They can also give rise to criminal liability and severe penalties.

Businesses also need to be aware that authorised government officers will soon be perfectly within their rights to demand access to their documents and premises, and to demand answers to questions in relation to Security of Payment Act issues.

If you or someone you know wants more information or needs help or advice, please contact us on +61 (0)2 9248 3450 or email info@bradburylegal.com.au.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2019-03-04 06:26:282019-04-08 07:13:47The Fantastic Fourth: another NSW Security of Payment amendment

Security of Payment – More Changes

November 2018/in Security of Payment

On 21 November 2018, the NSW government passed the Building and Construction Industry Security of Payment Amendment Act 2018.

This will make changes to the security of payment regime, and will take effect when the government announces so in the NSW Government Gazette.

So what are the main changes that builders and developers need to be aware of?

  • A payment claim must once again state that it is made under the Building and Construction Industry Security of Payment Act 1999 (“endorsement”);
  • Progress payments to a subcontractor are now due and payable 20 business days after a payment claim is issued (previously: 30 business days);
  • The ‘reference date’ system for payment claims is abolished. Now, where the contract is silent on dates for serving payment claims, a payment claim may be served on the last day of the month that construction work was first carried out under the contract, and then for the last day of each month of work afterwards;
  • Where a contract is terminated, a payment claim may be made from the date of termination;
  • If a head contractor company issues a payment claim to a principal and provides a supporting statement that is known to be false or misleading, then any company director who knows about this false or misleading statement can be convicted of an offence;
  • The Minister for Innovation and Better Regulation may make codes of practice to be observed by adjudicating organisations, and may cancel an adjudicating organisation’s authority for non-compliance with these;
  • Once a corporation is in liquidation, it cannot serve payment claims or enforce them;
  • Authorised officers from the Department of Finance, Services and Innovation now have extensive powers for the purposes of investigating, monitoring and enforcing compliance with the Act; and
  • Maximum penalties for various provisions have been increased.

The amendments also confirm what the High Court has already decided: that there are very limited grounds for appealing the decision of an adjudicator once it is made.

Other changes have also been made. These changes do not apply to any contract entered into before the amendments take effect. If you’d like to know more, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-11-27 22:13:552018-11-28 04:46:08Security of Payment – More Changes

Challenging Adjudication Determinations – some recent guidance

September 2018/in Security of Payment

Parties to a commercial building dispute may utilise Security of Payment (SOP) legislation in their jurisdiction to resolve payment claims and recover money owing under a construction contract.

Disputes are resolved quickly by an adjudicator and any amount determined as owing must be paid within the statutory timeframe. The determination is enforceable but without prejudice to the common law rights of either party. Due to the limited time in which an adjudicator must determine a payment dispute, it is not surprising that a determination may come before the Court for judicial review.

The grounds for review have been visited by various Courts with the following cases providing insight as to what might (and might not) justify having an adjudication determination quashed.

No review avenues for non-jurisdictional error

The High Court in Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4 confirmed that parties to an adjudication determination under the Building and Construction Security of Payment Act 1999 (NSW) may not seek judicial review for non-jurisdictional error of law.

The Court reiterated the nature of the (NSW) Act which, amongst other things, was intended to ‘reform payment behaviour in the construction industry’ by ensuring prompt recovery of payment for work carried out under a construction contract. The legislation is ‘coherent, expeditious and self-contained’ and ‘not concerned with finally and conclusively determining the entitlements of parties to a construction contract’.

Accordingly, an adjudicator is sanctioned to make a determination and a Court is not empowered to quash that decision for non-jurisdictional error, even if based on an incorrect interpretation of the subject contract.

An adjudication determination may only be set aside on grounds of jurisdictional error – an error going to the authority or power of the adjudicator, such as non-compliance with procedural requirements under SOP legislation.

Minimum standards required when assessing an adjudication determination

Nuance Group (Australia) Pty Limited (Nuance) v Shape Australia Pty Limited (Shape)[2018] VSC 362 provides guidance as to when a Court might quash an adjudication determination.

Shape served a payment claim on Nuance for over $3.5 million for demolition and associated works at Melbourne International Airport. Nuance responded with a payment schedule stating the amount payable as nil. Shape applied for adjudication for the sum of $2,243,105.55. An amount of $1,400,007.12 was determined payable, which after an adjudication review instigated by Nuance, was reduced to $1,216,715.72.

Nuance challenged the validity of both the original and reviewed determination in the Supreme Court of Victoria.

Nuance submitted that the adjudicator had not determined the amount of the progress claim as required by SOP legislation, which as a minimum necessitated a finding of whether the work identified in the relevant claim had in fact been performed and the value of that work. Rather, the adjudicator had deducted what he considered were excluded amounts from Shape’s claim to arrive at the revised figure and, in doing so, failed to comply with ‘basic and essential requirements’ of the Act.

Nuance was successful, and the adjudication determination was quashed.

Whilst acknowledging the tight timeframes under which adjudicators are required to operate, Justice Digby nonetheless conceded that the adjudicator had:

‘…failed to undertake the required task of addressing the payment claim and payment schedule and, consider those parameters of the dispute between the claimant and the respondent as to what claimed work … had been carried out under the Contract and what the value of that work … was.’

The adjudicator had merely worked back from the original claim in a manner that did not constitute a ‘fair and reasonable consideration’ of the determination providing ‘no sufficiently comprehensible reasons and basis for the amount determined’.

An adjudicator’s reasons must be considered in context

Southern Cross Electrical Engineering (Southern Cross) v Steve Magill Earthmoving (Magill) [2018] NSWSC 1027 considered another appeal of an adjudication decision.

Essentially, Southern Cross disputed Magill’s payment claim, which comprised additional amounts for excavation work based on trenching some areas of the subject site that were wider than stipulated in the contract. Southern Cross submitted that the adjudicator had erred by requiring it to prove that there had been no variation to the contract and that the earthmoving works had been over-claimed.

Relying on Justice Vickery’s lengthy series of matters to consider in Plenty Road Pty Ltd v Construction Engineering (Aust) Pty Ltd [2015] VSC 631, Southern Cross claimed that the adjudicator was required to ‘examine all the material for himself, and to come to a conclusion, based on that material as to what amount (if any) is payable.’

Justice McDougall acknowledged the processes set out by Justice Vickery were applicableto a determination however rejected any requirement for them to be ‘applied serially and mechanically in every case.’ Rather, the adjudicator’s reasons must be considered in context which included ‘the content of the dispute as established by the payment claim and the payment schedule, and the parties’ elaboration of that dispute.’

Further, the reasoning must be assessed considering the interim nature of an adjudicator’s determination under SOP legislation, the voluminous material to be dealt with, the strict timeframe and the fact that adjudicators are not usually lawyers.

Cross Engineering’s appeal was dismissed, Justice McDougall concluding that:

‘Factually, the adjudicator’s approach may have been (and probably was) incorrect. It is no doubt something that could have been improved upon if the adjudicator had “world enough and time”. But looking at his approach … I am far from persuaded that it was unreasonable to the extent that it must be taken to invalidate his determination’.

Conclusion

An adjudication determination is not subject to judicial review for non-jurisdictional error.

An adjudicator must apply certain minimum standards when assessing an adjudication application, however his or her reasoning will be considered in the context of the purpose and intent of the legislation, that being for the timely resolution of payment disputes under a construction contract. A decision that emanates from an error of law not associated with a jurisdictional error, will generally not entitle the Court to intervene.

Security of Payments legislation across Australia has been the subject of review and proposed reform. The recent release of the Murray Report recommends the national harmonisation of SOP laws and the implementation of review rights for parties (by a review adjudicator) for determinations concerning amounts of $100,000 or more.

If implemented, construction industry participants should have greater clarity regarding the circumstances under which an aggrieved party can challenge an adjudication determination.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-09-18 15:25:082018-09-19 07:27:48Challenging Adjudication Determinations – some recent guidance

When adjudication certificates meet statutory demands

July 2018/in Security of Payment

Parties to a payment dispute in the commercial building industry may utilise the Building and Construction Industry Security of Payment Act 1999 (NSW) (the ‘SOPA’) to resolve the matter.

The Act provides an efficient means of recovering money owed for construction work by invoking a statutory right for a contractor to receive progress payments under a contract.

Disputes are usually resolved quickly by an adjudicator. A determination is made which, in most cases, requires a respondent to pay the claimant a specified amount within the statutory timeframe. The determination is enforceable but without prejudice to the common law rights of either party. If the respondent fails to pay, the claimant may apply for an adjudication certificate which can be filed in Court to obtain judgement against the respondent.

When additional attempts are made under other legislation to enforce payment of the debt the matter can become complex.

Powerpark Systems Pty Ltd [2018] NSWSC 793 considers the interplay between the state-based SOPA and the issue of a statutory demand under the Commonwealth’s Corporations Act 2001. The case recognises the policy supporting the adjudication process and emphasises the need for parties to act quickly if they wish to challenge a determination.

The case and the decision

Powerpark Pty Ltd (Powerpark) retained Shoemark Electrical Pty Ltd (Shoemark) to install solar panels at various sites. Shoemark invoiced Powerpark for $44,811.11 for services carried out in New South Wales and Queensland and subsequently issued a payment claim under the SOPA.

Powerpark responded to the claim by issuing a payment schedule complaining of Shoemark’s defective work at building sites, agreeing to pay $24,956.97, and threatening to pursue Shoemark for rectification costs if the defective work was not resolved.

Shoemark proceeded to have the claim adjudicated which was determined in its favour for $44,811.11. Relying on the adjudication certificate, Shoemark served a statutory demand on Powerpark under the Corporations Act 2001. (The effect of serving a statutory demand is that a company will be presumed insolvent if, after 21 days it fails to pay the debt or is unsuccessful in having the demand set aside by a Court.)

Subsequently, and pursuant to the SOPA, Shoemark obtained judgment against Powerpark from the Local Court for $48,230.74 being the amount determined under adjudication plus fees and interest.

Powerpark applied to the Supreme Court to have the statutory demand set aside on the following grounds:

  • There was a genuine dispute about the existence or amount of the debt due to a purported jurisdictional error affecting the adjudication certificate and judgment.

One of the contracts for which the adjudication was determined related to work performed in Queensland. Powerpark claimed that as the SOPA expressly excluded work performed outside of New South Wales, the adjudication was ‘beyond the jurisdiction of the adjudicator’. It followed that the judgement issued by the Local Court in reliance of the adjudication certificate should be void.

The Court rejected this argument. Although the SOPA does not apply to work performed outside of New South Wales that in itself, was insufficient to invalidate the judgement. Whilst a potentially erroneous decision is reviewable, once the adjudication certificate is filed the debt is nevertheless payable.

Although Powerpark may have applied for judicial review to stay the judgement for jurisdictional error, its’ time for commencing proceedings had expired and it failed to explain any reason for not commencing or delaying proceedings.

  • The jurisdictional error constituted ‘some other reason’ as to why the demand should be set aside in accordance with s 459(1)(b) of the Corporations Act 2001.

Powerpark was again unsuccessful on this argument. The Court has discretion regarding what may constitute ‘some other reason’ to have a statutory demand set aside however, ‘the pendency of curial proceedings’ was, without more, insufficient to establish ‘some other reason.’

  • Powerpark had an offsetting claim against Shoemark comprising the losses claimed due to defective work.

On this point Powerpark was again unsuccessful in having the statutory demand set aside. It did however convince the Court of its offsetting claim resulting in the amount of the statutory demand being reduced to $21,483.14 which took into account the defective works.

Key takeaways

  • A judgment arising from the filing of an adjudication certificate determines that the judgment debt is indisputably due and payable. The legislative policy supporting the SOPA is to facilitate payment of an adjudicated amount notwithstanding the potential of a ‘curial dispute’ which, if later established could be cured by restitution.
  • An offsetting claim (in respect of a statutory demand) may be ordered by a Court without disturbing the validity of an adjudication certificate or the statutory demand.
  • Once a judgment debt issues, the subject of an adjudication certificate, a respondent will face difficulties in challenging its validity. Obtaining early advice during any construction payment dispute is important to ensure the merits of the proceedings and relevant timeframes are considered.

If you or someone you know wants more information or needs help or advice, please contact us on +612 9248 3450 or email info@bradburylegal.com.au.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-07-10 09:59:532019-06-20 23:43:26When adjudication certificates meet statutory demands

National review of security of payment legislation by John Murray AM

June 2018/in Security of Payment

The long-awaited national review of security of payment legislation by John Murray AM has been released.

The ‘Murray Report’ recommends harmonised security of payment laws across Australia by selecting various provisions of each state’s and territory’s model and emphasises the importance of the Commonwealth, states and territories working together to implement those recommendations.

Some of the key recommendations of the Murray Report:

  1. Reference dates to be replaced with an entitlement to make a payment claim every named month, or more frequently if so provided under the contract;
  1. Payment claims to identify a detailed breakdown of the amount claimed; the time period within which the respondent is to provide a payment schedule; and should be endorsed as a claim made under the legislation (among other related requirements);
  1. Supporting statements to accompany payment claims submitted to a head contractor to the principal (requiring a statement that subcontractors and suppliers have been paid);
  1. All adjudicators are to be trained, registered, graded and appointed to disputes by a new regulator;
  1. The introduction of statutory trusts for subcontractor payment and the adoption of an extended Christmas shutdown period; and
  1. Any parts of an adjudicator’s decision that falls into jurisdictional error, but does not affect the whole of the decision, can be severed;
  1. Claimants to be entitled to withdraw and make a new application if an adjudicator has not accepted its application within 4 business days, an adjudicator fails to determine an application within the prescribed timeframe or an adjudicator has given notice of their withdrawal from the adjudication;
  1. Parties entitled to make an application for a review of an adjudication determination if the adjudicated amount is equal to or greater than $100,000 of the scheduled amount, or $100,000 (or more) lower than the claimed amount.

The Australian Government is working with the states and territories through the Building Ministers’ Forum (BMF) to consider and respond to the findings and recommendations of the Murray Report.  Responsibility for this project has now transferred to the Department of Industry, Innovation and Science which provides secretariat support to the BMF.

We will keep you posted on developments and look forward to the proposed harmonisation of security of payment legislation.

Regards Brendan and Scott

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2018-06-15 13:46:122018-08-17 14:40:05National review of security of payment legislation by John Murray AM

No notice needed: NSW Court of Appeal rules on enforcement of Security of Payment Act determination

March 2017/in Security of Payment

In the recent unanimous decision of Fitz Jersey Pty Ltd v Atlas Construction Group Pty Ltd [2017] NSWCA 53, the Court of Appeal considered the enforcement of a judgment (pursuant to an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act)) by garnishee order and without notice of the judgment being given to the unsuccessful respondent.

The Court of Appeal confirmed:

  • the long-held view that notice of the entry of and enforcement of a judgment (obtained pursuant to an adjudication determination) is not required; and
  • that, when applying for a garnishee order, a party is not required to disclose to the Court that an unsuccessful respondent to an adjudication determination has commenced proceedings challenging the adjudication determination underlying the judgment (unless there are special circumstances, such as a stay or undertaking has been sought).

Background

The background to the Court of Appeal’s decision can be briefly summarised as follows.

1. On 6 January 2017, an adjudicator determined an adjudication application in favour of the builder in the amount of $10,748,466.31 plus interest and the adjudicator’s fees.

2. On 13 January 2017, the developer was required to pay to the builder the adjudicated amount plus interest and the adjudicator’s fees in accordance with section 23 of the Act.

3. On 13 January 2017, the developer did not pay the adjudicated amount to the builder.  Instead, the developer filed and served a Summons and List Statement in the Technology and Construction List of the Supreme Court of NSW seeking an order that the adjudication determination be quashed.  The letter to the builder’s solicitor serving the Summons and List Statement relevantly said:

“We are instructed that if your client seeks an order at that directions hearing that our client lodge the amount of the adjudication determination with the Supreme Court until a judgment is issued on our client’s summons, our client will not object to that order being made.” 

4. On 16 January 2017, the builder requested an adjudication certificate for the adjudicated amount and the amounts for interest and the adjudicator’s fees.

5. On 17 January 2017, the builder received the adjudication certificate in the amount of $11,023,619.76 and filed the certificate as a judgment of the Supreme Court.  Later, on 17 January 2017, the builder applied for a garnishee order against NAB in respect of the judgment amount.

6. On 27 January 2017, the Supreme Court issued the garnishee order against NAB for the amount of the judgment debt.  Later, on 27 January 2017, the garnishee order was served on NAB.

7. On 2 February 2017, NAB paid the full amount of the judgment debt to the builder.

8. On 3 February 2017, the developer became aware of the judgment, the garnishee order and the payment by NAB.

Supreme Court application

On 6 February 2017, the developer made an application to the Supreme Court seeking orders that the amount paid pursuant to the garnishee order be repaid into Court.  The developer’s application was based on two grounds.

  1. The developer primarily submitted that, because the developer did not have notice of the builder’s application for an adjudication certificate or the entry of judgment, the developer had been deprived of an alleged entitlement or right under section 25 of the Act to pay the money into Court pending the determination of the validity of the determination.
  2. The developer also relied on a secondary argument that the proceedings commenced by the developer to have the adjudication determination quashed should have been disclosed in the builder’s application for a garnishee order.

The Supreme Court dismissed the application.  The Court did not consider it appropriate to deal with the developer’s argument under section 25 of the Act on an urgent application and said that it did not consider that an applicant for a garnishee order needed to put any additional material before the Court (other than as required by the Uniform Civil Procedure Rules 2005 (NSW) (Rules), which prescribes the form and requirements for an application for a garnishee order).

In any event, at a more fundamental level, the Court cited the developer’s failure to obtain an injunction or seek an undertaking restraining the enforcement of the adjudication determination as reasons why the Court would not exercise its discretion to grant the equitable relief sought by the developer.

Court of Appeal decision

The developer appealed the Supreme Court’s decision on three grounds, the first of which was essential for the other grounds to succeed.

  1. The Supreme Court incorrectly exercised its discretion in refusing equitable relief.
  2. The builder was required to notify the developer that a judgment had been obtained before taking steps to enforce it.
  3. When applying for a garnishee order, the builder was required to notify the Court that the developer had commenced proceedings to review the underlying adjudication determination.

Is there an obligation to notify of a judgment pursuant to an adjudication determination before enforcement?

In short, no.  The Court of Appeal considered section 25 of the Act, in conjunction with the Rules in respect of the entry and enforcement of judgments.

Relevantly, section 25 of the Act provides as follows.

“25   Filing of adjudication certificate as judgment debt

(1)       An adjudication certificate may be filed as a judgment for a debt in any court of competent jurisdiction and is enforceable accordingly.

(2)       An adjudication certificate cannot be filed under this section unless it is accompanied by an affidavit by the claimant stating that the whole or any part of the adjudicated amount has not been paid at the time the certificate is filed.

(3)       If the affidavit indicates that part of the adjudicated amount has been paid, the judgment is for the unpaid part of that amount only.

(4)       If the respondent commences proceedings to have the judgment set aside, the respondent:

(a)       is not, in those proceedings, entitled:

(i)        to bring any cross-claim against the claimant, or

(ii)       to raise any defence in relation to matters arising under the construction contract, or

(iii)      to challenge the adjudicator’s determination, and

(b)       is required to pay into the court as security the unpaid portion of the adjudicated amount pending the final determination of those proceedings.”

For various reasons, including those noted below, the Court found that there is no obligation on a party that registers an adjudication certificate as a judgment to notify the other party that a judgment has been entered.

  • Rule 36.14 of the Rules provides that a judgment need not be served unless expressly required by the Rules.  The Rules were introduced after the operation of the Act.  There is no express requirement in the Act or the Rules that a judgment must be served or notified to the other party.
  • The proposition that a judgment cannot be enforced without service on the other party “has no support in authority, or as a matter of general principle.  It would, on its face, be inconsistent with the proposition that service is not required”, as per Rule 36.14 (as noted above).
  • Section 25(4) of the Act does not put the unsuccessful party in a better position than any other judgment debtor (upon which service of a judgment is not required before enforcement).  The effect of section 25(4) on an unsuccessful respondent to an adjudication determination is restrictive.
  • Section 25(4)(b) of the Act operates to require payment into Court of the unpaid portion of the adjudicated amount, if any (pending the determination by the Court of whether or not the judgment should be set aside).  It does not require there to be an unpaid portion.
  • To require notice of the existence of a judgment would deny the effect of the words “enforceable accordingly” in section 25(1) of the Act: “There is no authority which seeks to adopt such a construction, nor does it fit with either the context in which s 25(1) appears, the objects of the Act, or anything in the legislative history.”

Interestingly, the Court of Appeal was at pains to clarify that section 25(4) of the Act does not confer any right to have a judgment set aside.  The Court’s power to set aside a judgment is founded in the Rules and in the inherent jurisdiction of the Court.

Further, the Court said that section 25(4)(b) of the Act, which requires the adjudicated amount to be paid into Court pending the Court’s determination of an application to set aside a judgment based on an adjudication determination, would not apply to an application to quash a determination before judgment has been entered (although, in practice, the Courts have required payment into Court of the adjudicated amount pending the determination of the challenge to the validity of the determination, by analogy to section 25(4)(b) of the Act).

Is there an obligation to disclose a challenge to an adjudication determination when applying for a garnishee order?

In short, no.  However, there may be circumstances where additional disclosure is required in an application for a garnishee order (or other ex parte application).  The extent of such disclosure will depend on the facts of the case and may include, for example, if an undertaking not to enforce has been sought and an application to seek a stay has been foreshadowed.

The Court of Appeal found, amongst other things.

  • The statutory context of an application for a garnishee order to enforce an adjudication under the Act is critical.  The payments under the Act are interim in nature (subject to final determination as contemplated by section 32 of the Act) and any reduction in the entitlement of a builder to enforce an adjudication determination would undermine the statutory purpose of the Act.  The fact that the judgment is interim and subject to a further final determination (as contemplated by section 32 of the Act) lessens the obligation of disclosure.
  • As per the Rules, an application for a garnishee order may be dealt with in the absence of the parties and need not be served on the judgment debtor or the proposed garnishee.  That accords with public policy reasons that judgment debtors should not be notified so that they do not take steps to avoid payment, e.g. transferring assets.
  • The question which must ultimately be determined is whether any fact disclosed would have been likely to affect the outcome of the application – otherwise setting an order aside is “an entirely penal exercise, which must be proportionate to the consequences for the party in breach”.
  • Therefore, the onus was on the developer to establish that the builder should be deprived of an entitlement to immediate payment of the determined amount on an interim basis, i.e. the developer needed to demonstrate reasonable prospects of success on its application for judicial review and that it may not be possible to recover the money from the builder, neither of which had been established by the developer in this case.

What does this mean for me?

1. If you are successful in an adjudication determination:

(a) judgment can be obtained by registering an adjudication certificate and there is no need to notify the respondent to the adjudication determination, even if the respondent has commenced proceedings to challenge the validity of the adjudication determination; and

(b) the judgment may be enforced by garnishee order and the extent to which an application for a garnishee order must disclose a challenge to the validity of the determination will depend on the steps taken by the unsuccessful respondent.  If the respondent has merely commenced proceedings challenging the determination (and not sought an undertaking or an injunction), no disclosure is required.

2. If you are unsuccessful in an adjudication determination and do not intend to pay the adjudicated amount by the time prescribed in the Act, you should seek an undertaking from the successful party that it will not enforce the determination until the Court rules on the validity of the determination.  If no undertaking is provided, an urgent injunction should be sought.

CONTACT US

Ground Floor
437 Kent Street
Sydney NSW 2000
 +612 9248 3450
info@bradburylegal.com.au

FLEXIBLE APPROACH & FEE OPTIONS

We will set up fee structures that ensure you are only charged when we add value and not each time you pick up the phone or send an email.

If you don’t want to pay hourly rates, then don’t.

Ask us about our fixed fees and retainers.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-03-30 06:54:052018-08-20 06:55:50No notice needed: NSW Court of Appeal rules on enforcement of Security of Payment Act determination

Taking the Universal Serial Bus (USB) may result in a delayed service under the Security of Payment Act

March 2017/in Security of Payment

In 1999, the New South Wales parliament legislated to create the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act).

In 2000, IBM began selling the first USB flash drives commercially.  Other methods and mediums to quickly and conveniently communicate significant amounts of information have come and gone since 1999.

It is therefore unsurprising that the Act does not specifically address service of documents by different technological methods and mediums.  Whether communication by a method or medium of technology is effective service under the Act has been left to the courts to determine.  This can often be a critical issue because of the strict timeframes under the Act for the service of payment schedules, adjudication applications and adjudication responses.

In the Supreme Court of NSW case of Parkview Constructions Pty Ltd (Parkview) v Total Lifestyle Windows Pty Ltd t/as Total Concept Group (Total) [2017] NSWSC 194, the Court considered whether the mere delivery of a Universal Serial Bus (USB) drive, which contained adjudication application documents, was valid service of an adjudication application under the Act.

Relevant issues

On 12 December 2016, the adjudicator made an adjudication determination in favour of Total in the amount of $539,634.24 (including GST).  On 14 December 2016, Parkview commenced proceedings to have the adjudication determination quashed or set aside.

The lodgement and service of the adjudication application that led to the determination was, as the Court said, a “litany of errors”.  In short, Parkview made the following complaints about the adjudication, which were upheld by the Court and had the effect of invalidating the determination.

  1. The version of the adjudication application referred by the adjudication nominating authority to the adjudicator differed from the version lodged under the Act by Total.
  2. The adjudication application served on Parkview was not a copy of the adjudication application referred to the adjudicator.
  3. Parkview’s adjudication response was wrongly disregarded by the adjudicator (because the adjudicator accepted that delivery of a USB stick amounted to valid service of an adjudication application under the Act and therefore determined that the adjudication response was out of time).
  4. The adjudicator took into account material that was not properly part of the adjudication application.

Is the delivery of a USB effective service under the Act?

Section 17(3)(a) of the Act provides that an adjudication application must be in writing.  Section 17(5) of the Act provides that a copy of an adjudication application must be served on the respondent.

Section 21(1) of the Interpretations Act 1987 (NSW) defines “writing” as:

“includes printing, photography, photocopying, lithography, typewriting and any other mode of representing or reproducing words in visible form.”

In construing sections 17(3)(a) and 17(5) of the Act with section 21 of the Interpretation Act 1987 (NSW), the Court held that service of the USB stick could not be equated with service of writing stored on it, and that the USB stick was not “writing” within the meaning of section 17(3)(a) of the Act.

Ultimately, the Court determined that mere delivery of an adjudication application on a USB drive does not amount to service of an adjudication application in accordance with the Act.

Accordingly, the Court found that Parkview was served with the adjudication application on 10 November 2016 when an employee of Parkview first opened the documents on the USB stick.  The effect of this decision was that Parkview’s adjudication response was within time and incorrectly disregarded by the adjudicator (a denial of procedural fairness and jurisdictional error).

Lodgement and service of the adjudication application

Section 17(5) of the Act provides that a “copy” of an adjudication application must be served on the respondent.  Section 19(1) of the Act provides that the adjudication application must be referred to the adjudicator by the nominating authority.  There were substantial and material (not trivial) differences in the versions of the adjudication application that were:

  • lodged with the nominating authority;
  • provided to the adjudicator by the adjudication nominating authority; and
  • served on Parkview.

The effect of the above was that there was a failure to comply with the essential prerequisites for a valid adjudication determination because:

  1. a copy of the adjudication application was not provided to Parkview in accordance with section 17(5) of the Act; and
  2. the adjudication was not properly referred to the adjudicator in accordance with section 19(1) of the Act.

The Court did not conclusively find that an identical copy of the adjudication application must be served on the respondent.  The Court expressly acknowledged that there may be scope to allow for “trivial” differences in certain circumstances.  In this case, the differences could not be labelled “trivial”.

What does this mean for me?

The issues that infected this adjudication arose from a failure to properly and carefully lodge and serve the adjudication application and a failure to ensure that a hard copy of the adjudication application was identical to the electronic version.  The timeframes under the Act are short and there are time pressures to lodge and serve documents, which can lead to irretrievable errors.

Some practical tips for avoiding the pitfalls evidenced in the Parkview case are set out below.

1. The Act expressly allows service by: (1) delivering it to the person personally; (2) lodging it during normal business hours at the person’s ordinary place of business; (3) sending it by post or facsimile addressed to the person’s ordinary place of business; or (4) as prescribed by the construction contract.

If possible, service of documents under the Act should be by courier to the person’s ordinary place of business during normal business hours to avoid any uncertainty or argument about whether the documents have been served.  A report from the courier confirming delivery should be obtained for evidentiary purposes.

2. Parties should note that service by USB stick is not effective service under the Act – the documents provided on the USB stick will only be served when opened and that would be difficult to evidence if contested by a respondent.  In short, documents should not be served by USB stick.

3. Service by email will only be effected once the documents have been accessed by the recipient.  This is difficult to evidence if contested.  For this reason, absent a contractual entitlement to serve documents by sending an email, service by email should be avoided.  Despite this, if email is used, ‘read receipts’ should be requested for evidentiary purposes.

4. If providing a hard copy of documents that have already been served electronically, ensure the hard copy is identical to the electronic version to avoid confusion and ambiguity, which could invalidate an adjudicator’s determination.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-03-09 06:51:572018-08-20 06:56:31Taking the Universal Serial Bus (USB) may result in a delayed service under the Security of Payment Act

‘The suspense is killing me’ – when do reference dates continue to accrue under the Security of Payment Act?

January 2017/in Security of Payment

The High Court has determined that a reference date is a precondition to a valid payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) with its landmark judgment in Southern Han Breakfast Point Pty Ltd (in Liquidation) v Lewence Construction Pty Ltd [2016] HCA 52.  Whether or not a reference date exists will continue to be contentious in security of payment disputes and the High Court decision is likely to lead to an increase in security of payment disputes coming before courts.

The decision also creates uncertainty around when a reference date will accrue and raises doubts about a number of Supreme Court decisions in respect of the accrual of reference dates and contracting out of the Act.  The High Court has adopted a much more literal interpretation of the wording of the Act than lower courts, which have regarded the objects and purposes of the Act as paramount.  In our opinion, the decision may ultimately result in an amendment to the wording of section 8 of the Act.

It is the first time the High Court has considered security of payment legislation in Australia and the decision will affect similar security of payment regimes to New South Wales, being all states and territories except Western Australia and the Northern Territory.

Facts

Southern Han Breakfast Point Pty Ltd (Southern Han) engaged Lewence Construction Pty Ltd (Lewence) to construct an apartment block for a contract sum of approximately $15.6 million (Contract).  On 27 October 2014, Southern Han gave Lewence notice to show cause in relation to alleged breaches of contract.  Despite alleged compliance with this request, the work was subsequently taken out of the hands of Lewence.  Lewence characterised the allegedly invalid taking of the work out of its hands as a repudiatory act and purported to accept that repudiation, with the effect that the Contract was terminated.

Under the Contract, reference dates accrued on the “8th day of each calendar month for work under the contract done to the 7th day of that month.”  A payment claim had previously been served on 8 October 2014 for work carried out to 7 October 2014, and on 4 December 2014 Lewence served what purported to be another payment claim.  This later claim failed to identify the reference date to which it related and concerned works carried out prior to 27 October 2014, including prior to 7 October 2014.

Decision and its effect

The High Court decision includes the following important points.

1. Reference date is precondition to a valid payment claim

The first issue before the court was whether a reference date is a precondition to a valid payment claim. This turned on the meaning and interpretation of section 13(1) of the Act, which defines those who are entitled to make a payment claim.  Lewence argued that the phrase “who is or who claims to be entitled to a progress payment” was purposefully expansive so as to apply to circumstances where a reference date had not arisen.  The court rejected this argument finding rather that the two-part description of those who may make a payment claim illustrates the distinction the Act makes between “present entitlement to progress payment and future ascertainment of the amount of the progress payment.”

From this the court held that all those making a payment claim must fall within the scope of section 8(1) of the Act, which grants such entitlement only “on and from each reference date under the construction contract” and as such concluded that a reference date under the contract is a precondition to the making of a valid payment claim.

2. Affirmation of one payment claim per reference date

The court provided further clarification as to the mechanics of section 13 generally, making it clear that not only must each payment claim be made in relation to a reference date, but that only one payment claim may be made in relation to a reference date.  A payment claim purportedly made that contravenes either of these requirements is not a payment claim under the Act, and is therefore incapable of ‘triggering’ the operation of Part 3 of the Act.  This affirms existing authority (see Dualcorp Pty Ltd v Remo Constructions Pty Ltd [2009] NSWCA 69 and Kitchen Xchange v Formacon Building Servics [2014] NSWSC 1602).

3. No reference dates accrue after termination (unless clear contractual intention)

A further issue before the court was the process by which a reference date is determined and ancillary to this, whether reference dates continue to arise after the termination of the Contract.  The court found that reference dates do not accrue after termination of the contract, unless there is a clearly expressed intention otherwise.

4. Accrual of reference dates can be suspended by operation of contract

The High Court found that there was no prohibition on Southern Han suspending payment and suspending the accrual of reference dates in reliance on clauses in the Contract.  The Court found that taking work out of Lewence’s hands had the effect of suspending the entirety of clause 37 of the Contract, including the accrual of reference dates.

5. When a reference date accrues depends on contract

The Court considered section 8(2) of the Act (set out below).

“(2)  In this section, reference date, in relation to a construction contract, means:

(a)  a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out (or related goods and services supplied or undertaken to be supplied) under the contract, or

(b)  if the contract makes no express provision with respect to the matter—the last day of the named month in which the construction work was first carried out (or the related goods and services were first supplied) under the contract and the last day of each subsequent named month.”

The Court confirmed that, if the Contract makes express provision for the accrual of reference dates, only section 8(2)(a) of the Act has work to do (i.e. the default reference date on the last day of each month only applies if a contract does not deal with reference dates).  Therefore, it is open to parties to agree on when reference dates will accrue and the circumstances around the accrual of reference dates.

It appears that the High Court was not required (or asked to) consider in what circumstances the no contracting out provision in section 34 of the Security of Payment Act may render such a clause void.

What does this mean for me?

The High Court decision is very important for construction industry stakeholders and the decision will affect principals and contractors in different ways.  All stakeholders should review and tailor construction contracts in light of the High Court’s decision.  Particular issues for principals and contractors to consider are set out below.

For principals

  • A reference date must exist for a contractor to make a valid payment claim.  A payment claim that is not in respect of a reference date will not be a valid payment claim under the Act.  Notwithstanding, principals should still always issue a payment schedule within 10 business days of receipt of a payment claim or a purported payment claim.  The payment schedule can still state that a reference date does not exist to validate the purported payment claim.
  • The High Court’s view is that the contract is king when it comes to determining when a reference date accrues.  Therefore, it is open to parties to agree on the circumstances when a reference date will arise.  Principals have previously attempted to impose conditions on the accrual of reference dates or provided that reference dates accrue after the occurrence of a specified event, but these conditions have generally been declared void for contracting out of the Act.  The High Court decision, which approves parties contracting to suspend the accrual of reference dates, provides some hope to principals that agreed conditions on the accrual of reference dates may be upheld.
  • To avoid doubt, construction contracts should state that reference dates do not accrue after termination of a contract.  Principals can take some comfort from the High Court’s decision in this regard.
  • Principals may wish to include other circumstances that result in suspension of payment and therefore also seek to suspend the accrual of reference dates.

For contractors

  • Contractors should ensure that there is a clear, unconditional and simple provision in their construction contracts for reference dates to accrue (on a monthly or milestone basis).
  • Contractors should also require an additional clause providing for reference dates to continue to accrue after termination of the contract, particularly if termination arises out of the principal’s breach of contract.  Alternatively, contractors should carefully consider their position before terminating a contract because reference dates will not accrue after termination and contractors will lose their rights to apply for adjudication.
  • Contractors should minimise the circumstances in which the accrual of reference dates and payment can be suspended to avoid being prevented from making a valid payment claim under the Act.
https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-01-31 06:56:382018-08-20 06:57:20‘The suspense is killing me’ – when do reference dates continue to accrue under the Security of Payment Act?

Summer of section 69: non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives

January 2017/in Security of Payment

The New South Wales Court of Appeal has confirmed that an adjudication determination under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Security of Payment Act) can only be quashed if there is a jurisdictional error of law.

The decision of the unanimous five-judge bench in Shade Systems Pty Ltd v Probuild Constructions (Aust) Pty Ltd (No 2) [2016] NSWCA 379 overturns the Supreme Court’s decision to quash an adjudication determination for non-jurisdictional errors of law on the face of the record.

The Court of Appeal decision also affirms its earlier decision in Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421, which has been followed in numerous decisions of the Supreme Court of NSW (and in courts of other states and territories).

Court of Appeal’s decision

The question in this case was whether the Supreme Court can exercise its supervisory jurisdiction to quash an adjudicator’s determination for errors of law on the face of the record.  There was no dispute between the parties that:

  1. the adjudicator had made errors of law in his adjudication determination; and
  2. the errors of law were not jurisdictional errors.

Under section 69(3) of the Supreme Court Act 1970 (NSW) (SC Act), the Supreme Court has a supervisory jurisdiction empowering it to quash determinations of courts and tribunals that include errors of law on the face of the record.

Section 69(5) of the SC Act provides that section 69(3) of the SC Act (power to quash determinations for error of law on the face of the record) does not “affect the operation of any legislative provision to the extent to which the provision is…effective to prevent the Court from exercising its powers to quash or otherwise review a decision.”

In essence, the Supreme Court can quash a determination of a court or tribunal (including an adjudication determination) unless there is a legislative provision that prevents the Court from doing so.

Ultimately, the Court of Appeal found that the Supreme Court cannot exercise that jurisdiction to quash adjudication determinations if there are only errors of law on the face of the record and that there must be jurisdictional error for the Court to intervene.

The Court of Appeal’s decision considered the tension between section 69(3) of the SC Act and the Security of Payment Act.  In arriving at its decision, the Court of Appeal observed the following.

  1. The Security of Payment Act does not provide for an appeal mechanism, which supports the view that errors of law (other than jurisdictional errors of law) should not be subject of review by Courts.  On the other hand, there is no section of the Security of Payment Act that expressly precludes the Supreme Court from reviewing adjudication determinations for errors of law on the face of the record (as apparently contemplated by section 69(5) of the SC Act).  To resolve this tension, the Court of Appeal considered the content, structure and practical operation of the Security of Payment Act.
  2. The procedure provided for by the Security of Payment Act would be undermined if the Supreme Court could review adjudication determinations for errors of law on the face of the record.  The effect of such reviews would be to stifle the objects and purpose of the Security of Payment Act, which is to provide a quick mechanism for payment disputes and maintain cashflow in the construction industry.
  3. Section 25(4) of the Security of Payment Act provides that an adjudication determination cannot be challenged and allowing an appeal under section 69(3) of the SC Act would be inconsistent with the Security of Payment Act, but the Court concluded that this was a relatively weak factor.
  4. The consistent approach of courts in New South Wales (and other states) has been to follow the decision in Brodyn that adjudication determinations cannot be quashed only for errors of law on the face of the record.  The Court of Appeal concluded that no sufficient reason has been put forward to doubt the decision in Brodyn (as to there being any ground other than jurisdictional error to quash an adjudication determination).

The Court of Appeal found that there was a legislative intention by the scheme of the Security of Payment Act that adjudication determinations would not be subject of review for non-jurisdictional errors of law.

Obiter comments in Lewence put to bed

Interestingly, the five-judge bench of the Court of Appeal in Shade Systems was entirely different to the composition of the three-judge bench of the Court of Appeal in Lewence Constructions Pty Ltd v Southern Han Breakfast Point Pty Ltd [2015] NSWCA 288.  The Lewence decision was handed down in September 2015.

The Lewence decision, which was not referred to in Shade Systems, was overturned by the High Court on 21 December 2016, but not for reasons going to the difference between the issue of jurisdictional error and non-jurisdictional error.

In the Lewence Court of Appeal decision, obiter comments were made to the effect that adjudication determinations could be quashed for errors of law on the face of the record.  That decision was made by their Honours Emmett JA (the judge at first instance in Shade Systems), Ward JA and Sackville AJA.

In Lewence:

  • Emmett JA made no reference to quashing the determination for an error of law on the face of the record, however (as noted above) Emmett JA was the judge in first instance in Shade Systems who determined that adjudication determinations could be quashed for errors of law on the face of the record.
  • Ward JA said at [71]:

“This Court was not taken to adjudicator’s reasons to suggest that there was any error of law on the face of the record in relation to the existence of an available reference date.”

It is implicit in the above that her Honour considered such an argument was available to quash an adjudication determination.

  • Sackville AJA said at [126]:

The footnote at [1] referred to section 69 of the SC Act, which sets out the supervisory jurisdiction of the Supreme Court to quash court or tribunal proceedings that include an error of law on the face of the record.  Accordingly, his Honour clearly envisaged that adjudication determinations could be quashed for errors of law on the face of the record.

Having regard to the above, on a purely speculative basis, there may have been a different outcome in Shade Systems if the Court of Appeal bench had been comprised of different judges.

Summary

Unless there is a jurisdictional error of law, an adjudication determination will not be quashed by the Supreme Court.  That is so even despite errors of law by an adjudicator in their determination.  This decision, like Brodyn, is likely to be followed in states and territories with similar legislative regimes (all states and territories except the NT and WA).

There is clearly some divergence of opinion within the Court of Appeal on this issue and the Court of Appeal in Shade Systems has placed great significance on the objects and purposes of the Security of Payment Act evincing an intention for section 69(3) of the SC Act not to apply to adjudication determinations.  There is clear acknowledgement in the Shade Systems decision of the tension between section 69(3) of the SC Act and the purpose of the Security of Payment Act.

The unanimous five-judge verdict in Shade Systems is a clear signal that the Court of Appeal does not want to or see the need to tinker with the precedent established in Brodyn (and the volume of authority that has followed that decision).

It appears that High Court intervention will now be required before errors of law on the face of the record mean that an adjudication determination can be quashed by courts in New South Wales.  The High Court first intervened in security of payment legislation on 21 December 2016.  In that decision, the High Court adopted a literal and plain English interpretation (rather than purposive) interpretation of the Security of Payment Act.  A similar approach to reviewing the Court of Appeal’s decision in Sun Shades may result in adjudication determinations being reviewable for non-jurisdictional errors of law.  However, until the High Court intervenes, non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives.

https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png 0 0 bradburylegal https://www.bradburylegal.com.au/wp-content/uploads/2018/08/BRADBURY_LEGAL_FINAL_REV_transparent.png bradburylegal2017-01-24 06:57:272018-08-20 06:58:10Summer of section 69: non-jurisdictional errors of law under the Security of Payment Act have had the best days of their lives
Page 4 of 6«‹23456›»

Categories

  • Commercial Issues
  • Construction Regulation
  • Contract Issues
  • Disputes
  • Security of Payment
  • Uncategorized

Archive

  • June 2025
  • May 2025
  • April 2025
  • March 2025
  • February 2025
  • May 2023
  • April 2023
  • February 2023
  • January 2023
  • November 2022
  • October 2022
  • September 2022
  • August 2022
  • July 2022
  • May 2022
  • March 2022
  • February 2022
  • December 2021
  • November 2021
  • October 2021
  • September 2021
  • August 2021
  • July 2021
  • June 2021
  • May 2021
  • February 2021
  • January 2021
  • November 2020
  • October 2020
  • September 2020
  • August 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020
  • February 2020
  • January 2020
  • November 2019
  • September 2019
  • July 2019
  • June 2019
  • May 2019
  • April 2019
  • March 2019
  • January 2019
  • November 2018
  • October 2018
  • September 2018
  • July 2018
  • June 2018
  • April 2018
  • March 2017
  • January 2017
  • December 2016
  • October 2016
  • June 2016
  • May 2016
  • April 2016
  • February 2016
  • November 2015
  • October 2015
  • September 2015
  • August 2015
  • July 2015
  • June 2015
  • April 2015
  • March 2015
  • February 2015
  • October 2014

Our Address

Suite 30.04, 201 Elizabeth Street
Sydney NSW 2000
02 9030 7400  |  info@bradburylegal.com.au

About Bradbury Legal

We are a boutique law firm providing high quality, personalised legal services to the property, development and construction industries.

Liability limited by a scheme approved under Professional Standards Legislation © Copyright - Bradbury Legal
  • LinkedIn
  • Mail
  • Instagram
  • Facebook
Scroll to top